Assessment Year | 2017 |
---|---|
Principal Product | Hydraulic pumps and motors |
NAICS | 333911: Pump and Pumping Equipment Manufacturing |
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $50 M to 100M |
# of Employees | 259 |
Plant Area |
184,000
ft2
|
Annual Production | 180,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $665,035 | 10,845,400 |
kWh
|
$0.061 |
Electricity Demand | $192,469 | 23,715 |
kW-mo/yr
|
$8.12 |
Natural Gas | $15,852 | 2,229 |
MMBtu
|
$7.11 |
TOTAL YEARLY COSTS | $873,356 | |||
RECOMMENDED SAVINGS* | $135,158 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,078 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $64,592 | $221,073 |
$47,219
770,296
kWh
|
$11,234
-
kW-mo/yr
|
- | $6,139 | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $375 | $75 |
$252
4,118
kWh
|
$58
-
kW-mo/yr
|
- | $65 | - | |
03 | 2.7135: Install occupancy sensors | $798 | $400 |
$798
13,024
kWh
|
- | - | - | - | |
04 | 2.2612: Use cooling tower water instead of refrigeration | $62,705 | $158,000 |
$42,413
691,892
kWh
|
$26,225
-
kW-mo/yr
|
- | - |
$(-5,933.0)
-
Tgal
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,666 | $500 |
$3,139
51,205
kWh
|
$727
-
kW-mo/yr
|
$(-100.0) | $(-100.0) | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $3,022 | $1,200 |
$3,022
49,280
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $135,158 | $381,248 |
$96,843
1,579,815
kWh
|
$38,244
-
kW-mo/yr
|
$(-100.0) | $6,104 |
$(-5,933.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $72,078 | $223,173 |
$54,178
883,805
kWh
|
$11,961
-
kW-mo/yr
|
$(-100.0) | $6,039 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs