| Assessment Year | 2016 |
|---|---|
| Principal Product | Fiber optic cables |
| NAICS | 335921: Fiber Optic Cable Manufacturing |
| SIC | 3357: Drawing and Insulating of Nonferrous Wire |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
55,000
ft2
|
| Annual Production | 800,000
units
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $23,157 | 498,881 |
kWh
|
$0.046 |
| Electricity Demand | $27,694 | 2,400 |
kW-mo/yr
|
$11.54 |
| Natural Gas | $4,081 | 565 |
MMBtu
|
$7.22 |
| TOTAL YEARLY COSTS | $54,932 | |||
| RECOMMENDED SAVINGS* | $23,445 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $12,087 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $7,250 | $500 | - |
$7,250
-
kW-mo/yr
|
- | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $4,087 | $100 |
$(-10,875.0)
-
kWh
|
$14,962
-
kW-mo/yr
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,862 | $21,540 |
$5,239
112,917
kWh
|
$4,014
-
kW-mo/yr
|
$1,609 | |
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $750 | $475 |
$384
8,280
kWh
|
$319
-
kW-mo/yr
|
$47 | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $338 | $100 |
$252
5,431
kWh
|
$86
-
kW-mo/yr
|
- | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $158 | $300 |
$158
3,399
kWh
|
- | - | |
| TOTAL RECOMMENDED | $23,445 | $23,015 |
$(-4,842.0)
130,027
kWh
|
$26,631
-
kW-mo/yr
|
$1,656 | ||
| TOTAL IMPLEMENTED | $12,087 | $1,075 |
$(-10,491.0)
8,280
kWh
|
$22,531
-
kW-mo/yr
|
$47 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs