Assessment Year | 2016 |
---|---|
Principal Product | Transmissions |
NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 1,200 |
Plant Area |
1,400,000
ft2
|
Annual Production | 800,000
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,891,610 | 49,051,800 |
kWh
|
$0.039 |
Electricity Demand | $826,236 | 90,384 |
kW-mo/yr
|
$9.14 |
Electricity Fees | $(-271,259.0) | - |
|
- |
Natural Gas | $215,465 | 63,245 |
MMBtu
|
$3.41 |
TOTAL YEARLY COSTS | $2,662,052 | |||
RECOMMENDED SAVINGS* | $578,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $188,251 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $306,868 | $500 |
$306,868
-
kWh
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $179,170 | $887,700 |
$102,173
2,646,960
kWh
|
$43,674
-
kW-mo/yr
|
- | - | $33,323 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,495 | $22,028 |
$3,476
90,053
kWh
|
- | - | - | $1,019 | |
04 | 2.7135: Install occupancy sensors | $2,121 | $3,123 |
$2,121
54,945
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,081 | $200 |
$6,911
179,040
kWh
|
$2,950
-
kW-mo/yr
|
- | $(-300.0) | $(-480.0) | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,342 | $100 |
$5,844
151,408
kWh
|
$2,498
-
kW-mo/yr
|
- | - | - | |
07 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $10,217 | $33,300 |
$5,896
152,755
kWh
|
$4,321
-
kW-mo/yr
|
- | - | - | |
08 | 2.2628: Utilize a less expensive cooling method | $8,890 | $25,230 |
$6,828
176,880
kWh
|
$2,062
-
kW-mo/yr
|
- | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $24,551 | $78,500 |
$17,211
445,980
kWh
|
$7,340
-
kW-mo/yr
|
- | - | - | |
10 | 2.4322: Use or replace with energy efficient substitutes | $25,240 | $100,000 |
$(-8,098.0)
(-209,790)
kWh
|
$(-3,465.0)
-
kW-mo/yr
|
$36,803
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $578,975 | $1,150,681 |
$449,230
3,688,231
kWh
|
$59,380
-
kW-mo/yr
|
$36,803
-
MMBtu
|
$(-300.0) | $33,862 | ||
TOTAL IMPLEMENTED | $188,251 | $887,900 |
$109,084
2,826,000
kWh
|
$46,624
-
kW-mo/yr
|
- | $(-300.0) | $32,843 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs