ITAC Assessment: NC0532
ITAC logo
ITAC Assessment: NC0532
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Plywood
NAICS 321212: Softwood Veneer and Plywood Manufacturing
SIC 2436: Softwood Veneer and Plywood
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 300,000
ft2
Annual Production 300,000
thousand feet
Production Hrs. Annual 8,400
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,283,657 35,024,400
kWh
Electricity Demand $595,682 58,582
kW-mo/yr
Natural Gas $31,692 4,921
MMBtu
Wood $344,172 1,209,647
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $150,231 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $51,648

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Wood Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $48,749 $105,000 $41,447
1,130,900
kWh
$16,048
-
kW-mo/yr
$(-8,746.0)
-
MMBtu
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $29,143 $73,960 $23,087
629,933
kWh
$9,152
-
kW-mo/yr
- - $(-3,096.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $773 $240 $235
6,412
kWh
$89
-
kW-mo/yr
- - $449
04 2.7142: Utilize higher efficiency lamps and/or ballasts $353 $438 $233
6,350
kWh
$92
-
kW-mo/yr
- - $28
05 2.1243: Use heat from boiler blowdown to preheat boiler feed water $18,636 $45,000 - - $18,636
-
MMBtu
- -
06 2.2113: Repair or replace steam traps $17,917 $8,000 - - $21,047
-
MMBtu
$(-250.0) $(-2,880.0)
07 2.2136: Install / repair insulation on steam lines $1,753 $1,620 - - $1,753
-
MMBtu
- -
08 2.2135: Repair and eliminate steam leaks $990 $450 - - $990
-
MMBtu
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $15,703 $500 $11,245
306,815
kWh
$4,458
-
kW-mo/yr
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,952 $100 $4,320
117,871
kWh
$1,712
-
kW-mo/yr
- $(-600.0) $(-480.0)
11 2.5123: Reduce fluid flow rates $8,338 $5,000 $5,971
162,926
kWh
$2,367
-
kW-mo/yr
- - -
12 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,924 $1,935 $2,082
56,800
kWh
$842
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $150,231 $242,243 $88,620
2,418,007
kWh
$34,760
-
kW-mo/yr
$33,680
-
MMBtu
$(-850.0) $(-5,979.0)
TOTAL IMPLEMENTED $51,648 $121,708 $23,555
642,695
kWh
$9,333
-
kW-mo/yr
$21,379
-
MMBtu
- $(-2,619.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Wood Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs