Assessment Year | 2014 |
---|---|
Principal Product | High voltage cable |
NAICS | 335929: Other Communication and Energy Wire Manufacturing |
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $50 M to 100M |
# of Employees | 120 |
Plant Area |
303,281
ft2
|
Annual Production | 1,970
thousand feet
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $350,803 | 10,726,394 |
kWh
|
$0.033 |
Electricity Demand | $130,036 | 20,074 |
kW-mo/yr
|
$6.48 |
Electricity Fees | $(-70,781.0) | - |
|
- |
Natural Gas | $57,583 | 6,356 |
MMBtu
|
$9.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.212: Adopt in-house material generation | $26,905 | $50,000 |
$(-7,663.0)
(-234,346)
kWh
|
$(-3,032.0)
-
kW-mo/yr
|
- | $(-2,400.0) | $40,000 | |
02 | 2.7135: Install occupancy sensors | $3,351 | $1,591 |
$3,351
102,464
kWh
|
- | - | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $1,741 | $7,000 |
$1,741
53,246
kWh
|
- | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $66 | $25 |
$30
924
kWh
|
$17
-
kW-mo/yr
|
- | - | $19 | |
05 | 2.7134: Use photocell controls | $165 | $160 |
$165
5,040
kWh
|
- | - | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $390 | $990 |
$64
1,944
kWh
|
$67
-
kW-mo/yr
|
- | - | $259 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,104 | $12,169 |
$1,705
52,135
kWh
|
$710
-
kW-mo/yr
|
- | - | $689 | |
08 | 2.4239: Eliminate or reduce compressed air usage | $2,554 | $5,000 |
$1,830
55,950
kWh
|
$724
-
kW-mo/yr
|
- | - | - | |
09 | 2.2437: Recover waste heat from equipment | $2,306 | $5,000 | - | - |
$2,306
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $40,582 | $81,935 |
$1,223
37,357
kWh
|
$(-1,514.0)
-
kW-mo/yr
|
$2,306
-
MMBtu
|
$(-2,400.0) | $40,967 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs