Assessment Year | 2014 |
---|---|
Principal Product | Gas cylinders |
NAICS | 332420: Metal Tank (Heavy Gauge) Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 104 |
Plant Area |
120,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 8,712
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $487,864 | 8,144,678 |
kWh
|
$0.060 |
Electricity Demand | $72,366 | 17,144 |
kW-mo/yr
|
$4.22 |
Electricity Fees | $2,634 | - |
|
- |
Natural Gas | $269,330 | 45,834 |
MMBtu
|
$5.88 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $61,403 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $38,469 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $23,503 | $100 |
$143,154
-
kWh
|
$(-120,627.0)
-
kW-mo/yr
|
$976 | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $13,824 | $50,000 |
$2,670
44,867
kWh
|
$570
-
kW-mo/yr
|
- |
$10,584
-
MMBtu
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $4,388 | $5,250 | - | - | - |
$4,388
-
MMBtu
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,509 | $10,000 |
$5,339
89,734
kWh
|
$571
-
kW-mo/yr
|
- |
$(-2,401.0)
-
MMBtu
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,436 | $50 |
$3,105
52,209
kWh
|
$331
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,983 | $100 |
$5,530
92,938
kWh
|
$593
-
kW-mo/yr
|
- | - | $(-900.0) | $(-240.0) | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,002 | $7,540 |
$1,873
23,418
kWh
|
$129
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $3,435 | $868 |
$3,435
42,933
kWh
|
- | - | - | - | - | |
09 | 2.4237: Substitute compressed air cooling with water or air cooling | $1,213 | $1,017 |
$1,061
17,840
kWh
|
$152
-
kW-mo/yr
|
- | - | - | - | |
10 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,110 | $200 |
$508
-
kWh
|
$602
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $61,403 | $75,125 |
$166,675
363,939
kWh
|
$(-117,679.0)
-
kW-mo/yr
|
$976 |
$12,571
-
MMBtu
|
$(-900.0) | $(-240.0) | ||
TOTAL IMPLEMENTED | $38,469 | $8,858 |
$157,605
211,498
kWh
|
$(-118,972.0)
-
kW-mo/yr
|
$976 | - | $(-900.0) | $(-240.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs