Assessment Year | 2013 |
---|---|
Principal Product | Commercial display shelving |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 2541: Wood Office and Store Fixtures, Partitions, Shelving, and Lockers |
Sales Range | $10 M to 50M |
# of Employees | 145 |
Plant Area |
387,000
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 2,250
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $216,156 | 2,933,000 |
kWh
|
$0.074 |
Electricity Demand | $125,076 | 9,362 |
kW-mo/yr
|
$13.36 |
Electricity Fees | $(-17,857.0) | - |
|
- |
Natural Gas | $31,925 | 3,434 |
MMBtu
|
$9.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $208,869 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $147,842 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $59,689 | $250,000 |
$4,953
67,200
kWh
|
$87,960
-
kW-mo/yr
|
$(-28,224.0)
-
MMBtu
|
- | - | - | $(-5,000.0) | - | |
02 | 3.1182: Make a new by-product | $86,815 | $250,000 |
$(-6,185.0)
(-83,925)
kWh
|
- | - | - |
$93,000
-
lb
|
- | - | - | |
03 | 2.7229: Air condition only space necessary | $4,146 | $200 |
$2,329
31,600
kWh
|
$1,817
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.5123: Reduce fluid flow rates | $34,287 | $18,000 |
$16,941
229,861
kWh
|
$17,346
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,558 | $100 |
$1,649
22,380
kWh
|
$449
-
kW-mo/yr
|
- | - | - | $(-300.0) | - | $(-240.0) | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,293 | $125 |
$1,627
22,079
kWh
|
$1,666
-
kW-mo/yr
|
- | - | - | - | - | - | |
07 | 2.4239: Eliminate or reduce compressed air usage | $577 | $875 |
$577
7,825
kWh
|
- | - | - | - | - | - | - | |
08 | 2.6218: Turn off equipment when not in use | $9,389 | $7,000 |
$9,389
127,395
kWh
|
- | - | - | - | - | - | - | |
09 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $286 | $750 |
$141
1,916
kWh
|
$145
-
kW-mo/yr
|
- | - | - | - | - | - | |
10 | 3.4155: Meter waste water | $4,155 | $4,200 | - | - | - |
$4,155
-
Tgal
|
- | - | - | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $456 | $2,704 |
$226
3,060
kWh
|
$230
-
kW-mo/yr
|
- | - | - | - | - | - | |
12 | 2.7111: Reduce illumination to minimum necessary levels | $3,622 | $775 |
$1,586
21,505
kWh
|
$1,623
-
kW-mo/yr
|
- | - | - | - | - | $413 | |
13 | 2.7135: Install occupancy sensors | $596 | $1,565 |
$596
8,088
kWh
|
- | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $208,869 | $536,294 |
$33,829
458,984
kWh
|
$111,236
-
kW-mo/yr
|
$(-28,224.0)
-
MMBtu
|
$4,155
-
Tgal
|
$93,000
-
lb
|
$(-300.0) | $(-5,000.0) | $173 | ||
TOTAL IMPLEMENTED | $147,842 | $281,275 |
$27,913
378,720
kWh
|
$22,901
-
kW-mo/yr
|
- |
$4,155
-
Tgal
|
$93,000
-
lb
|
$(-300.0) | - | $173 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs