ITAC Assessment: NC0493
ITAC logo
ITAC Assessment: NC0493
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Denim
NAICS 313210: Broadwoven Fabric Mills
SIC 2211: Broadwoven Fabric Mills, Cotton
Sales Range $10
M
to 50
M
# of Employees 225
Plant Area 737,500
ft2
Annual Production 24,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,840,180 45,234,000
kWh
Electricity Demand $881,472 96,816
kW-mo/yr
Electricity Fees $748 -
Natural Gas $91,462 20,083
MMBtu
Other Gas $1 205,909
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $181,097 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $107,257

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $40,789 $215,791 $24,756
608,261
kWh
$16,033
-
kW-mo/yr
- - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,370 $36,172 $3,724
91,495
kWh
$4,520
-
kW-mo/yr
- - - $126
03 2.7135: Install occupancy sensors $3,826 $7,934 $3,826
94,000
kWh
- - - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,550 $1,386 $520
12,780
kWh
$159
-
kW-mo/yr
- - - $871
05 2.1113: Reduce combustion air flow to optimum $37,850 $6,372 - - $51,415
-
MMBtu
- $(-1,325.0) $(-12,240.0)
06 2.2511: Insulate bare equipment $15,385 $1,820 - - $15,385
-
MMBtu
- - -
07 2.2136: Install / repair insulation on steam lines $853 $1,447 - - $853
-
MMBtu
- - -
08 2.2121: Increase amount of condensate returned $13,410 $10,000 - - $4,707
-
MMBtu
$8,703
-
Tgal
- -
09 2.1241: Reduce excessive boiler blowdown $430 - - - $430
-
MMBtu
- - -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,165 $100 $5,045
123,948
kWh
$1,800
-
kW-mo/yr
- - $(-1,200.0) $(-480.0)
11 2.4226: Use / purchase optimum sized compressor $3,410 $15,000 $3,410
83,790
kWh
- - - - -
12 3.4113: Treat and reuse rinse waters $28,586 $90,000 - - - $28,586
-
Tgal
- -
13 4.512: Condense operation into one building $21,473 $10,000 $15,051
369,792
kWh
$6,086
-
kW-mo/yr
$336
-
MMBtu
- - -
TOTAL RECOMMENDED $181,097 $396,022 $56,332
1,384,066
kWh
$28,598
-
kW-mo/yr
$73,126
-
MMBtu
$37,289
-
Tgal
$(-2,525.0) $(-11,723.0)
TOTAL IMPLEMENTED $107,257 $233,649 $45,372
1,114,781
kWh
$24,078
-
kW-mo/yr
$52,181
-
MMBtu
- $(-2,525.0) $(-11,849.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs