| Assessment Year | 2013 |
|---|---|
| Principal Product | Catalyst modules |
| NAICS | 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing |
| SIC | 3269: Pottery Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
194,500
ft2
|
| Annual Production | 7,000
pieces
|
| Production Hrs. Annual | 4,950
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $158,508 | 2,821,430 |
kWh
|
$0.056 |
| Electricity Demand | $89,988 | 10,687 |
kW-mo/yr
|
$8.42 |
| Natural Gas | $422,566 | 66,538 |
MMBtu
|
$6.35 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $92,035 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,326 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,304 | $18,247 |
$6,070
108,519
kWh
|
$2,252
-
kW-mo/yr
|
- | - | $(-18.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,368 | $54,675 |
$10,625
189,129
kWh
|
$3,743
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7135: Install occupancy sensors | $7,283 | $8,778 |
$7,283
129,645
kWh
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,039 | $1,124 |
$380
6,760
kWh
|
$78
-
kW-mo/yr
|
- | - | $581 | |
| 05 | 2.7134: Use photocell controls | $2,065 | $250 |
$1,442
25,659
kWh
|
$623
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.2437: Recover waste heat from equipment | $56,670 | $60,000 | - | - |
$56,670
-
MMBtu
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,306 | $100 |
$2,308
41,081
kWh
|
$838
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | |
| TOTAL RECOMMENDED | $92,035 | $143,174 |
$28,108
500,793
kWh
|
$7,534
-
kW-mo/yr
|
$56,670
-
MMBtu
|
$(-600.0) | $323 | ||
| TOTAL IMPLEMENTED | $34,326 | $82,050 |
$27,728
494,033
kWh
|
$7,456
-
kW-mo/yr
|
- | $(-600.0) | $(-258.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs