ITAC Assessment: NC0484
ITAC logo
ITAC Assessment: NC0484
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Catalyst modules
NAICS 327110: Pottery, Ceramics, and Plumbing Fixture Manufacturing
SIC 3269: Pottery Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 194,500
ft2
Annual Production 7,000
pieces
Production Hrs. Annual 4,950
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,508 2,821,430
kWh
Electricity Demand $89,988 10,687
kW-mo/yr
Natural Gas $422,566 66,538
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $92,035 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,326

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $8,304 $18,247 $6,070
108,519
kWh
$2,252
-
kW-mo/yr
- - $(-18.0)
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,368 $54,675 $10,625
189,129
kWh
$3,743
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $7,283 $8,778 $7,283
129,645
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,039 $1,124 $380
6,760
kWh
$78
-
kW-mo/yr
- - $581
05 2.7134: Use photocell controls $2,065 $250 $1,442
25,659
kWh
$623
-
kW-mo/yr
- - -
06 2.2437: Recover waste heat from equipment $56,670 $60,000 - - $56,670
-
MMBtu
- -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,306 $100 $2,308
41,081
kWh
$838
-
kW-mo/yr
- $(-600.0) $(-240.0)
TOTAL RECOMMENDED $92,035 $143,174 $28,108
500,793
kWh
$7,534
-
kW-mo/yr
$56,670
-
MMBtu
$(-600.0) $323
TOTAL IMPLEMENTED $34,326 $82,050 $27,728
494,033
kWh
$7,456
-
kW-mo/yr
- $(-600.0) $(-258.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs