| Assessment Year | 2013 |
|---|---|
| Principal Product | Water meters |
| NAICS | 334514: Totalizing Fluid Meter and Counting Device Manufacturing |
| SIC | 3824: Totalizing Fluid Meters and Counting Devices |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
126,000
ft2
|
| Annual Production | 10
units
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $280,561 | 5,707,760 |
kWh
|
$0.049 |
| Electricity Demand | $73,727 | 10,945 |
kW-mo/yr
|
$6.74 |
| Electricity Fees | $726 | - |
|
- |
| Natural Gas | $16,186 | 1,914 |
MMBtu
|
$8.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $68,198 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,801 | $48,075 |
$23,919
486,662
kWh
|
$5,467
-
kW-mo/yr
|
- | - | $(-585.0) | |
| 02 | 2.7135: Install occupancy sensors | $9,597 | $5,600 |
$9,338
189,997
kWh
|
$259
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $975 | $1,124 |
$332
6,760
kWh
|
$62
-
kW-mo/yr
|
- | - | $581 | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $620 | $100 |
$1,188
24,170
kWh
|
$272
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | |
| 05 | 2.2437: Recover waste heat from equipment | $11,988 | $4,750 | - | - |
$11,988
-
MMBtu
|
- | - | |
| 06 | 2.5123: Reduce fluid flow rates | $16,217 | $25,000 |
$13,200
268,560
kWh
|
$3,017
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $68,198 | $84,649 |
$47,977
976,149
kWh
|
$9,077
-
kW-mo/yr
|
$11,988
-
MMBtu
|
$(-600.0) | $(-244.0) | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs