Assessment Year | 2012 |
---|---|
Principal Product | Upholstered furniture |
NAICS | 337121: Upholstered Household Furniture Manufacturing |
SIC | 2512: Wood Household Furniture, Upholstered |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
454,422
ft2
|
Annual Production | 36,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $111,042 | 1,756,770 |
kWh
|
$0.063 |
Electricity Demand | $34,708 | 8,817 |
kW-mo/yr
|
$3.94 |
Natural Gas | $6,778 | 819 |
MMBtu
|
$8.28 |
Wood | $1 | 4,500 |
MMBtu
|
$0.000 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,848 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,634 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $22,713 | $129,851 |
$16,349
258,684
kWh
|
$6,364
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $389 | $1,595 |
$187
2,958
kWh
|
$73
-
kW-mo/yr
|
$129 | |
03 | 2.7135: Install occupancy sensors | $769 | $1,200 |
$769
12,169
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $784 | $843 |
$320
5,070
kWh
|
$29
-
kW-mo/yr
|
$435 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $934 | $200 |
$680
10,760
kWh
|
$254
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,526 | - |
$1,098
17,380
kWh
|
$428
-
kW-mo/yr
|
- | |
07 | 2.5194: Redesign process | $12,445 | $25,000 |
$8,958
141,740
kWh
|
$3,487
-
kW-mo/yr
|
- | |
08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $288 | $860 |
$207
3,280
kWh
|
$81
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $39,848 | $159,549 |
$28,568
452,041
kWh
|
$10,716
-
kW-mo/yr
|
$564 | ||
TOTAL IMPLEMENTED | $26,634 | $133,349 |
$18,841
298,132
kWh
|
$7,229
-
kW-mo/yr
|
$564 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs