| Assessment Year | 2012 |
|---|---|
| Principal Product | Upholstered furniture |
| NAICS | 337121: Upholstered Household Furniture Manufacturing |
| SIC | 2512: Wood Household Furniture, Upholstered |
| Sales Range | $100 M to 500M |
| # of Employees | 900 |
| Plant Area |
600,000
ft2
|
| Annual Production | 187,000
pieces
|
| Production Hrs. Annual | 4,420
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $362,483 | 9,414,720 |
kWh
|
$0.039 |
| Electricity Demand | $639,935 | 29,742 |
kW-mo/yr
|
$21.52 |
| Electricity Fees | $6,125 | - |
|
- |
| Natural Gas | $188,009 | 21,874 |
MMBtu
|
$8.60 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $160,311 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $135,268 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,646 | $48,008 |
$7,536
195,746
kWh
|
$14,240
-
kW-mo/yr
|
- | - | - | $(-130.0) | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $77,055 | $212,514 |
$22,287
578,871
kWh
|
$54,768
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,178 | $15,554 |
$1,379
35,826
kWh
|
$3,799
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,681 | $1,690 |
$932
24,219
kWh
|
$2,739
-
kW-mo/yr
|
- | - | - | $10 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,103 | $1,892 |
$184
4,788
kWh
|
$542
-
kW-mo/yr
|
- | - | - | $377 | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $261 | $281 |
$65
1,690
kWh
|
$51
-
kW-mo/yr
|
- | - | - | $145 | |
| 07 | 2.7135: Install occupancy sensors | $781 | $1,425 |
$781
20,280
kWh
|
- | - | - | - | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,215 | $400 |
$1,587
41,217
kWh
|
$2,468
-
kW-mo/yr
|
- | - | $(-600.0) | $(-240.0) | |
| 09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,683 | $300 |
$1,441
37,437
kWh
|
$2,242
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 2.5121: Redesign flow to minimize mass transfer length | $24,300 | $5,000 |
$9,521
247,300
kWh
|
$14,779
-
kW-mo/yr
|
- | - | - | - | |
| 11 | 2.7313: Recycle air for heating, ventilation and air conditioning | $15,581 | $3,000 |
$1,062
27,576
kWh
|
$8,180
-
kW-mo/yr
|
$6,339
-
MMBtu
|
- | - | - | |
| 12 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,066 | $3,000 | - | - |
$2,066
-
MMBtu
|
- | - | - | |
| 13 | 2.2121: Increase amount of condensate returned | $854 | $2,000 | - | - |
$377
-
MMBtu
|
$477
-
Tgal
|
- | - | |
| 14 | 2.2121: Increase amount of condensate returned | $425 | $650 | - | - |
$425
-
MMBtu
|
- | - | - | |
| 15 | 2.2123: Insulate feedwater tank | $482 | $1,542 | - | - |
$482
-
MMBtu
|
- | - | - | |
| TOTAL RECOMMENDED | $160,311 | $297,256 |
$46,775
1,214,950
kWh
|
$103,808
-
kW-mo/yr
|
$9,689
-
MMBtu
|
$477
-
Tgal
|
$(-600.0) | $162 | ||
| TOTAL IMPLEMENTED | $135,268 | $290,433 |
$37,189
965,960
kWh
|
$88,978
-
kW-mo/yr
|
$9,207
-
MMBtu
|
$477
-
Tgal
|
$(-600.0) | $17 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs