Assessment Year | 2012 |
---|---|
Principal Product | Solid rubber wheels |
NAICS | 326299: All Other Rubber Product Manufacturing |
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 30 |
Plant Area |
53,000
ft2
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $76,173 | 2,247,300 |
kWh
|
$0.034 |
Electricity Demand | $39,665 | 4,220 |
kW-mo/yr
|
$9.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,816 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,160 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,790 | $14,320 |
$4,404
129,948
kWh
|
$1,771
-
kW-mo/yr
|
- | $(-385.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $444 | $1,674 |
$190
5,618
kWh
|
$254
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $252 | $533 |
$252
7,433
kWh
|
- | - | - | |
04 | 2.2623: Minimize condenser cooling water temperature | $2,656 | $1,800 |
$2,628
77,550
kWh
|
$1,086
-
kW-mo/yr
|
$(-1,058.0)
-
Tgal
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,516 | $4,075 |
$845
24,929
kWh
|
$671
-
kW-mo/yr
|
- | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $158 | $100 |
$185
5,460
kWh
|
$73
-
kW-mo/yr
|
- | $(-100.0) | |
TOTAL RECOMMENDED | $10,816 | $22,502 |
$8,504
250,938
kWh
|
$3,855
-
kW-mo/yr
|
$(-1,058.0)
-
Tgal
|
$(-485.0) | ||
TOTAL IMPLEMENTED | $8,160 | $20,702 |
$5,876
173,388
kWh
|
$2,769
-
kW-mo/yr
|
- | $(-485.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs