Assessment Year | 2012 |
---|---|
Principal Product | Lockers and shelving |
NAICS | 337215: Showcase, Partition, Shelving, and Locker Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
450,000
ft2
|
Annual Production | 37,200,000
lb
|
Production Hrs. Annual | 3,500
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $324,837 | 8,468,959 |
kWh
|
$0.038 |
Electricity Demand | $247,802 | 19,284 |
kW-mo/yr
|
$12.85 |
Natural Gas | $302,900 | 51,181 |
MMBtu
|
$5.92 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $338,572 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $321,587 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $31,614 | $21,400 |
$31,614
937,826
kWh
|
- | - | - | - | - | - | |
02 | 2.2437: Recover waste heat from equipment | $11,614 | $9,225 | - | - |
$11,614
-
MMBtu
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,109 | $100 |
$4,763
124,164
kWh
|
$2,186
-
kW-mo/yr
|
- | $(-600.0) | - | $(-240.0) | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,655 | $98,739 |
$12,323
321,255
kWh
|
$14,154
-
kW-mo/yr
|
- | - | $(-822.0) | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,286 | $973 |
$599
15,621
kWh
|
$687
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.2425: Use flue gases to heat process or service water | $632 | $2,035 |
$(-150.0)
(-3,917)
kWh
|
$(-173.0)
-
kW-mo/yr
|
$955
-
MMBtu
|
- | - | - | - | |
07 | 4.114: Add/modify equipment to improve drying process | $113,534 | $25,000 | - | - | - | - | - | - | $113,534 | |
08 | 4.131: Modify process to reduce material use/cost | $105,000 | $40,000 | - | - | - | - | - | $105,000 | - | |
09 | 4.121: Maintain clean conditions before painting | $38,389 | $30,000 |
$(-5,753.0)
(-149,975)
kWh
|
$(-6,608.0)
-
kW-mo/yr
|
- | - | - | - | $50,750 | |
10 | 4.424: Improve space comfort conditioning | $4,739 | $8,000 |
$(-403.0)
(-10,500)
kWh
|
$(-193.0)
-
kW-mo/yr
|
- | - | - | - | $5,335 | |
TOTAL RECOMMENDED | $338,572 | $235,472 |
$42,993
1,234,474
kWh
|
$10,053
-
kW-mo/yr
|
$12,569
-
MMBtu
|
$(-600.0) | $(-822.0) | $104,760 | $169,619 | ||
TOTAL IMPLEMENTED | $321,587 | $216,212 |
$43,546
1,248,891
kWh
|
$10,419
-
kW-mo/yr
|
- | $(-600.0) | $(-822.0) | $104,760 | $164,284 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs