Assessment Year | 2011 |
---|---|
Principal Product | Indoor air quality equipment |
NAICS | 333413: Industrial and Commercial Fan and Blower and Air Purification Equipment Manufacturing |
SIC | 3564: Industrial and Commercial Fans and Blowers and Air Purification Equipment |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
265,000
ft2
|
Annual Production | 25,000
pieces
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $170,076 | 3,198,000 |
kWh
|
$0.053 |
Electricity Demand | $83,312 | 9,800 |
kW-mo/yr
|
$8.50 |
Natural Gas | $111,682 | 15,085 |
MMBtu
|
$7.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,962 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $32,005 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $3,138 | $2,127 | - | - |
$3,138
-
MMBtu
|
- | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $3,152 | $14,895 |
$1,938
36,443
kWh
|
$1,214
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,424 | $1,000 |
$897
16,866
kWh
|
$527
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $142 | $100 |
$357
6,705
kWh
|
$205
-
kW-mo/yr
|
- | $(-300.0) | $(-120.0) | |
05 | 2.1224: Replace boiler | $5,957 | $26,400 | - | - |
$5,957
-
MMBtu
|
- | - | |
06 | 2.2514: Cover open tanks | $414 | $908 | - | - |
$414
-
MMBtu
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,609 | $32,453 |
$11,096
208,658
kWh
|
$8,513
-
kW-mo/yr
|
- | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,087 | $10,660 |
$1,804
33,915
kWh
|
$1,383
-
kW-mo/yr
|
- | - | $(-100.0) | |
09 | 2.4134: Replace electric motor with fossil fuel engine | $1,039 | $876 |
$410
7,710
kWh
|
$629
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $37,962 | $89,419 |
$16,502
310,297
kWh
|
$12,471
-
kW-mo/yr
|
$9,509
-
MMBtu
|
$(-300.0) | $(-220.0) | ||
TOTAL IMPLEMENTED | $32,005 | $63,019 |
$16,502
310,297
kWh
|
$12,471
-
kW-mo/yr
|
$3,552
-
MMBtu
|
$(-300.0) | $(-220.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs