Assessment Year | 2011 |
---|---|
Principal Product | Medium voltage transformers |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $50 M to 100M |
# of Employees | 225 |
Plant Area |
162,000
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $516,716 | 7,191,600 |
kWh
|
$0.072 |
Electricity Demand | $355,867 | 16,399 |
kW-mo/yr
|
$21.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $304,682 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,198 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $244,640 | $566,702 |
$3,443
47,780
kWh
|
$284,134
-
kW-mo/yr
|
$(-42,937.0)
-
MMBtu
|
- | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $30,535 | $5,000 | - |
$31,135
-
kW-mo/yr
|
- | $(-600.0) | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,540 | $37,837 |
$9,587
133,424
kWh
|
$10,853
-
kW-mo/yr
|
- | - | $100 | - | |
04 | 2.7135: Install occupancy sensors | $202 | $600 |
$202
2,816
kWh
|
- | - | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,663 | $100 |
$1,681
23,400
kWh
|
$1,822
-
kW-mo/yr
|
- | $(-600.0) | - | $(-240.0) | |
06 | 2.2511: Insulate bare equipment | $133 | $567 |
$133
1,852
kWh
|
- | - | - | - | - | |
07 | 4.212: Adopt in-house material generation | $5,969 | $25,000 |
$(-2,694.0)
(-37,495)
kWh
|
$(-3,059.0)
-
kW-mo/yr
|
- | - | $(-1,200.0) | $12,922 | |
TOTAL RECOMMENDED | $304,682 | $635,806 |
$12,352
171,777
kWh
|
$324,885
-
kW-mo/yr
|
$(-42,937.0)
-
MMBtu
|
$(-1,200.0) | $(-1,100.0) | $12,682 | ||
TOTAL IMPLEMENTED | $33,198 | $5,100 |
$1,681
23,400
kWh
|
$32,957
-
kW-mo/yr
|
- | $(-1,200.0) | - | $(-240.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs