ITAC Assessment: NC0417
ITAC logo
ITAC Assessment: NC0417
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Carbonated soft drinks
NAICS 312111: Soft Drink Manufacturing
SIC 2086: Bottled and Canned Soft Drinks and Carbonated Waters
Sales Range $50
M
to 100
M
# of Employees 110
Plant Area 245,000
ft2
Annual Production 32,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $379,707 7,579,500
kWh
Electricity Demand $220,644 20,187
kW-mo/yr
Natural Gas $269,927 39,944
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,898 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,199

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.2437: Recover waste heat from equipment $101,691 $362,675 $(-31,989.0)
(-638,000)
kWh
$(-19,711.0)
-
kW-mo/yr
$153,391
-
MMBtu
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,199 $100 $2,890
57,645
kWh
$1,149
-
kW-mo/yr
- $(-600.0) - $(-240.0)
03 2.2437: Recover waste heat from equipment $7,220 $2,500 - - $7,220
-
MMBtu
- - -
04 2.4239: Eliminate or reduce compressed air usage $739 $180 $645
12,867
kWh
$94
-
kW-mo/yr
- - - -
05 4.212: Adopt in-house material generation $26,671 $70,000 $(-11,750.0)
(-234,346)
kWh
$(-5,115.0)
-
kW-mo/yr
- - $(-2,400.0) $45,936
06 2.2113: Repair or replace steam traps $2,928 $1,000 - - $4,678
-
MMBtu
- $(-1,750.0) -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $168 $199 $95
1,899
kWh
$73
-
kW-mo/yr
- - - -
08 2.7135: Install occupancy sensors $2,865 $2,751 $2,865
57,146
kWh
- - - - -
09 2.7134: Use photocell controls $417 $122 $330
6,592
kWh
$87
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $145,898 $439,527 $(-36,914.0)
(-736,197)
kWh
$(-23,423.0)
-
kW-mo/yr
$165,289
-
MMBtu
$(-600.0) $(-4,150.0) $45,696
TOTAL IMPLEMENTED $3,199 $100 $2,890
57,645
kWh
$1,149
-
kW-mo/yr
- $(-600.0) - $(-240.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs