Assessment Year | 2010 |
---|---|
Principal Product | Perlite |
NAICS | 327992: Ground or Treated Mineral and Earth Manufacturing |
SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
Sales Range | $5 M to 10M |
# of Employees | 10 |
Plant Area |
8,275
ft2
|
Annual Production | 24,000,000
lb
|
Production Hrs. Annual | 4,800
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,778 | 820,000 |
kWh
|
$0.070 |
Electricity Demand | $12,034 | 2,461 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $2,459 | - |
|
- |
Natural Gas | $168,946 | 33,826 |
MMBtu
|
$4.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,976 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,008 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $11,924 | $26,000 | - | - |
$11,924
-
MMBtu
|
- | - | |
02 | 2.4151: Develop a repair/replace policy | $1,188 | $1,991 |
$1,012
14,398
kWh
|
$176
-
kW-mo/yr
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $1,044 | $680 |
$1,044
14,850
kWh
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,335 | $50 |
$1,137
16,176
kWh
|
$198
-
kW-mo/yr
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $305 | $100 |
$566
8,057
kWh
|
$99
-
kW-mo/yr
|
- | $(-300.0) | $(-60.0) | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $556 | $1,692 |
$525
7,462
kWh
|
$91
-
kW-mo/yr
|
- | $(-82.0) | $22 | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $488 | $562 |
$326
4,631
kWh
|
$81
-
kW-mo/yr
|
- | - | $81 | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $868 | $1,450 |
$790
11,232
kWh
|
$78
-
kW-mo/yr
|
- | - | - | |
09 | 2.7135: Install occupancy sensors | $268 | $499 |
$268
3,807
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $17,976 | $33,024 |
$5,668
80,613
kWh
|
$723
-
kW-mo/yr
|
$11,924
-
MMBtu
|
$(-382.0) | $43 | ||
TOTAL IMPLEMENTED | $5,008 | $6,344 |
$4,624
65,763
kWh
|
$723
-
kW-mo/yr
|
- | $(-382.0) | $43 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs