| Assessment Year | 2010 |
|---|---|
| Principal Product | Saft drinks and bottled water |
| NAICS | 312111: Soft Drink Manufacturing |
| SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
| Sales Range | $50 M to 100M |
| # of Employees | 120 |
| Plant Area |
90,000
ft2
|
| Annual Production | 18,200,000
pieces
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $189,922 | 4,446,240 |
kWh
|
$0.043 |
| Electricity Demand | $144,359 | 10,282 |
kW-mo/yr
|
$14.04 |
| Electricity Fees | $21,448 | - |
|
- |
| Natural Gas | $179,227 | 19,670 |
MMBtu
|
$9.11 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $75,259 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,026 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,881 | $100 |
$2,389
66,424
kWh
|
$1,332
-
kW-mo/yr
|
- | $(-600.0) | $(-240.0) | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,796 | $50 |
$2,437
67,769
kWh
|
$1,359
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.2123: Insulate feedwater tank | $283 | $337 | - | - |
$283
-
MMBtu
|
- | - | |
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,066 | $1,000 | - | - |
$1,066
-
MMBtu
|
- | - | |
| 05 | 2.2437: Recover waste heat from equipment | $67,233 | $190,000 |
$(-9,137.0)
(-254,100)
kWh
|
$(-8,563.0)
-
kW-mo/yr
|
$84,933
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $75,259 | $191,487 |
$(-4,311.0)
(-119,907)
kWh
|
$(-5,872.0)
-
kW-mo/yr
|
$86,282
-
MMBtu
|
$(-600.0) | $(-240.0) | ||
| TOTAL IMPLEMENTED | $8,026 | $1,487 |
$4,826
134,193
kWh
|
$2,691
-
kW-mo/yr
|
$1,349
-
MMBtu
|
$(-600.0) | $(-240.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs