| Assessment Year | 2010 |
|---|---|
| Principal Product | Transformers |
| NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
| SIC | 3612: Power, Distribution, and Specialty Transformers |
| Sales Range | $50 M to 100M |
| # of Employees | 180 |
| Plant Area |
126,000
ft2
|
| Annual Production | 2,500
pieces
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,174 | 1,553,845 |
kWh
|
$0.066 |
| Electricity Demand | $49,260 | 4,482 |
kW-mo/yr
|
$10.99 |
| Electricity Fees | $1,543 | - |
|
- |
| Natural Gas | $173,727 | 20,831 |
MMBtu
|
$8.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $40,517 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,843 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $25,103 | $60,000 | - | - |
$25,103
-
MMBtu
|
- | - | |
| 02 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $9,007 | $37,000 | - | - |
$9,007
-
MMBtu
|
- | - | |
| 03 | 2.2437: Recover waste heat from equipment | $4,571 | $11,072 |
$(-28.0)
(-500)
kWh
|
$(-20.0)
-
kW-mo/yr
|
$4,619
-
MMBtu
|
- | - | |
| 04 | 2.4151: Develop a repair/replace policy | $1,761 | $4,346 |
$1,110
19,916
kWh
|
$651
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $75 | $200 |
$312
5,600
kWh
|
$183
-
kW-mo/yr
|
- | $(-300.0) | $(-120.0) | |
| TOTAL RECOMMENDED | $40,517 | $112,618 |
$1,394
25,016
kWh
|
$814
-
kW-mo/yr
|
$38,729
-
MMBtu
|
$(-300.0) | $(-120.0) | ||
| TOTAL IMPLEMENTED | $10,843 | $41,546 |
$1,422
25,516
kWh
|
$834
-
kW-mo/yr
|
$9,007
-
MMBtu
|
$(-300.0) | $(-120.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs