Assessment Year | 2010 |
---|---|
Principal Product | Transformers |
NAICS | 335311: Power, Distribution, and Specialty Transformer Manufacturing |
SIC | 3612: Power, Distribution, and Specialty Transformers |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
126,000
ft2
|
Annual Production | 2,500
pieces
|
Production Hrs. Annual | 5,000
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $103,174 | 1,553,845 |
kWh
|
$0.066 |
Electricity Demand | $49,260 | 4,482 |
kW-mo/yr
|
$10.99 |
Electricity Fees | $1,543 | - |
|
- |
Natural Gas | $173,727 | 20,831 |
MMBtu
|
$8.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,517 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,843 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $25,103 | $60,000 | - | - |
$25,103
-
MMBtu
|
- | - | |
02 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $9,007 | $37,000 | - | - |
$9,007
-
MMBtu
|
- | - | |
03 | 2.2437: Recover waste heat from equipment | $4,571 | $11,072 |
$(-28.0)
(-500)
kWh
|
$(-20.0)
-
kW-mo/yr
|
$4,619
-
MMBtu
|
- | - | |
04 | 2.4151: Develop a repair/replace policy | $1,761 | $4,346 |
$1,110
19,916
kWh
|
$651
-
kW-mo/yr
|
- | - | - | |
05 | 2.2437: Recover waste heat from equipment | $75 | $200 |
$312
5,600
kWh
|
$183
-
kW-mo/yr
|
- | $(-300.0) | $(-120.0) | |
TOTAL RECOMMENDED | $40,517 | $112,618 |
$1,394
25,016
kWh
|
$814
-
kW-mo/yr
|
$38,729
-
MMBtu
|
$(-300.0) | $(-120.0) | ||
TOTAL IMPLEMENTED | $10,843 | $41,546 |
$1,422
25,516
kWh
|
$834
-
kW-mo/yr
|
$9,007
-
MMBtu
|
$(-300.0) | $(-120.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs