ITAC Assessment: NC0400
ITAC logo
ITAC Assessment: NC0400
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Transformers
NAICS 335311: Power, Distribution, and Specialty Transformer Manufacturing
SIC 3612: Power, Distribution, and Specialty Transformers
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 126,000
ft2
Annual Production 2,500
pieces
Production Hrs. Annual 5,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,174 1,553,845
kWh
Electricity Demand $49,260 4,482
kW-mo/yr
Electricity Fees $1,543 -
Natural Gas $173,727 20,831
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,517 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,843

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2414: Use waste heat from hot flue gases to preheat $25,103 $60,000 - - $25,103
-
MMBtu
- -
02 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating $9,007 $37,000 - - $9,007
-
MMBtu
- -
03 2.2437: Recover waste heat from equipment $4,571 $11,072 $(-28.0)
(-500)
kWh
$(-20.0)
-
kW-mo/yr
$4,619
-
MMBtu
- -
04 2.4151: Develop a repair/replace policy $1,761 $4,346 $1,110
19,916
kWh
$651
-
kW-mo/yr
- - -
05 2.2437: Recover waste heat from equipment $75 $200 $312
5,600
kWh
$183
-
kW-mo/yr
- $(-300.0) $(-120.0)
TOTAL RECOMMENDED $40,517 $112,618 $1,394
25,016
kWh
$814
-
kW-mo/yr
$38,729
-
MMBtu
$(-300.0) $(-120.0)
TOTAL IMPLEMENTED $10,843 $41,546 $1,422
25,516
kWh
$834
-
kW-mo/yr
$9,007
-
MMBtu
$(-300.0) $(-120.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs