ITAC Assessment: NC0398
ITAC logo
ITAC Assessment: NC0398
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Power tools
NAICS 333991: Power-Driven Handtool Manufacturing
SIC 3546: Power-Driven Handtools
Sales Range greater than $500
M
# of Employees 2,000
Plant Area 500,000
ft2
Annual Production 3,240,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,980,028 45,390,896
kWh
Electricity Demand $1,148,860 81,329
kW-mo/yr
Electricity Fees $8,435 -
Natural Gas $363,822 35,115
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $215,286 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $135,418

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7241: Install outside air damper / economizer on hvac unit $35,525 $20,000 $35,367
810,800
kWh
$158
-
kW-mo/yr
- - -
02 2.7245: Use direct air supply to exhaust hoods $68,552 $57,900 $32,084
735,525
kWh
$24,114
-
kW-mo/yr
$12,354
-
MMBtu
- -
03 2.7229: Air condition only space necessary $9,565 $18,450 $6,976
159,922
kWh
$2,589
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,697 $200 $7,782
178,404
kWh
$2,915
-
kW-mo/yr
- $(-4,800.0) $(-1,200.0)
05 2.2437: Recover waste heat from equipment $1,751 $14,000 - - $1,751
-
MMBtu
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,554 $1,205 $825
18,921
kWh
$729
-
kW-mo/yr
- - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $93,642 $225,498 $67,206
1,540,726
kWh
$25,138
-
kW-mo/yr
- $(-16,184.0) $17,482
TOTAL RECOMMENDED $215,286 $337,253 $150,240
3,444,298
kWh
$55,643
-
kW-mo/yr
$14,105
-
MMBtu
$(-20,984.0) $16,282
TOTAL IMPLEMENTED $135,418 $246,903 $111,180
2,548,851
kWh
$28,940
-
kW-mo/yr
- $(-20,984.0) $16,282
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs