ITAC Assessment: NC0397
ITAC logo
ITAC Assessment: NC0397
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Magnet wire
NAICS 331318: Other Aluminum Rolling, Drawing, and Extruding
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 56,500
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $129,024 1,362,800
kWh
Electricity Demand $83,407 6,762
kW-mo/yr
Electricity Fees $3,348 -
Natural Gas $3,348 300
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,579 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,203

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.4237: Substitute compressed air cooling with water or air cooling $12,960 $17,280 $8,799
213,043
kWh
$4,161
-
kW-mo/yr
- - - -
02 2.2437: Recover waste heat from equipment $712 $1,000 $(-521.0)
(-12,622)
kWh
$(-247.0)
-
kW-mo/yr
$1,413
-
MMBtu
- - $67
-
Tgal
03 2.2511: Insulate bare equipment $1,212 $3,660 $823
79,668
kWh
$389
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $492 $751 $331
8,019
kWh
$161
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $4,804 $12,206 $3,213
77,789
kWh
$1,522
-
kW-mo/yr
- $(-877.0) $946 -
06 2.7135: Install occupancy sensors $399 $100 $399
9,650
kWh
- - - - -
TOTAL RECOMMENDED $20,579 $34,997 $13,044
375,547
kWh
$5,986
-
kW-mo/yr
$1,413
-
MMBtu
$(-877.0) $946 $67
-
Tgal
TOTAL IMPLEMENTED $5,203 $12,306 $3,612
87,439
kWh
$1,522
-
kW-mo/yr
- $(-877.0) $946 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs