Assessment Year | 2009 |
---|---|
Principal Product | Conveyor rollers |
NAICS | 333922: Conveyor and Conveying Equipment Manufacturing |
SIC | 3535: Conveyors and Conveying Equipment |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
228,297
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $139,471 | 2,811,000 |
kWh
|
$0.050 |
Electricity Demand | $64,608 | 7,321 |
kW-mo/yr
|
$8.83 |
Electricity Fees | $3,040 | - |
|
- |
LPG | $7,091 | 415 |
MMBtu
|
$17.09 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $150,997 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $76,612 | $275,318 |
$23,560
427,281
kWh
|
$13,052
-
kW-mo/yr
|
- | - | $40,000 | |
02 | 4.512: Condense operation into one building | $31,185 | $13,100 |
$20,537
362,468
kWh
|
$8,544
-
kW-mo/yr
|
- |
$2,104
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $37,090 | $83,137 |
$26,319
475,983
kWh
|
$11,222
-
kW-mo/yr
|
- | - | $(-451.0) | |
04 | 2.7135: Install occupancy sensors | $600 | $558 |
$600
10,585
kWh
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $313 | $132 |
$102
1,800
kWh
|
$80
-
kW-mo/yr
|
- | - | $131 | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,507 | - |
$1,064
18,785
kWh
|
$443
-
kW-mo/yr
|
- | - | - | |
07 | 2.2437: Recover waste heat from equipment | $3,690 | $5,306 | - | - |
$3,690
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $150,997 | $377,551 |
$72,182
1,296,902
kWh
|
$33,341
-
kW-mo/yr
|
$3,690
-
MMBtu
|
$2,104
-
MMBtu
|
$39,680 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs