Assessment Year | 2008 |
---|---|
Principal Product | Dental equipment |
NAICS | 339114: Dental Equipment and Supplies Manufacturing |
SIC | 3843: Dental Equipment and Supplies |
Sales Range | $50 M to 100M |
# of Employees | 450 |
Plant Area |
169,000
ft2
|
Annual Production | 20,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,564 | 4,926,800 |
kWh
|
$0.030 |
Electricity Demand | $95,639 | 9,918 |
kW-mo/yr
|
$9.64 |
Electricity Fees | $7,670 | - |
|
- |
Natural Gas | $140,228 | 12,332 |
MMBtu
|
$11.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,522 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,168 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $4,343 | $15,000 |
$4,343
125,311
kWh
|
- | - | - | |
02 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $13,018 | $26,250 |
$3,992
115,161
kWh
|
$9,026
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $650 | $100 |
$1,053
30,390
kWh
|
$397
-
kW-mo/yr
|
$(-400.0) | $(-400.0) | |
04 | 2.2437: Recover waste heat from equipment | $4,993 | $16,000 |
$4,057
117,052
kWh
|
$936
-
kW-mo/yr
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,639 | $5,398 |
$2,920
84,250
kWh
|
$1,719
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,879 | $9,158 |
$1,865
53,808
kWh
|
$1,014
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $30,522 | $71,906 |
$18,230
525,972
kWh
|
$13,092
-
kW-mo/yr
|
$(-400.0) | $(-400.0) | ||
TOTAL IMPLEMENTED | $8,168 | $14,656 |
$5,838
168,448
kWh
|
$3,130
-
kW-mo/yr
|
$(-400.0) | $(-400.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs