Assessment Year | 2008 |
---|---|
Principal Product | Soft drinks |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
180,000
ft2
|
Annual Production | 30,000,000
pieces
|
Production Hrs. Annual | 8,600
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $519,764 | 13,505,930 |
kWh
|
$0.038 |
Electricity Demand | $300,679 | 24,254 |
kW-mo/yr
|
$12.40 |
Electricity Fees | $21,275 | - |
|
- |
Natural Gas | $397,877 | 42,349 |
MMBtu
|
$9.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $349,483 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $10,092 | $8,000 | - |
$10,092
-
kW-mo/yr
|
- | - | - | |
02 | 2.8112: Combine utility meters | $61,386 | $25,000 |
$61,386
-
kWh
|
- | - | - | - | |
03 | 2.1133: Adjust burners for efficient operation | $1,636 | $1,600 | - | - |
$1,636
-
MMBtu
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $255,208 | $500,000 |
$(-46,434.0)
(-1,332,000)
kWh
|
$(-30,902.0)
-
kW-mo/yr
|
$332,544
-
MMBtu
|
- | - | |
05 | 2.2511: Insulate bare equipment | $721 | $250 | - | - |
$721
-
MMBtu
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,090 | $50 |
$4,842
138,905
kWh
|
$2,248
-
kW-mo/yr
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,240 | $100 |
$2,773
79,550
kWh
|
$1,287
-
kW-mo/yr
|
- | $(-420.0) | $(-400.0) | |
08 | 2.4239: Eliminate or reduce compressed air usage | $10,110 | $8,000 |
$6,903
198,030
kWh
|
$3,207
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $349,483 | $543,000 |
$29,470
(-915,515)
kWh
|
$(-14,068.0)
-
kW-mo/yr
|
$334,901
-
MMBtu
|
$(-420.0) | $(-400.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs