ITAC Assessment: NC0340
ITAC logo
ITAC Assessment: NC0340
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Corrugated packing
NAICS 322211: Corrugated and Solid Fiber Box Manufacturing
SIC 2670:
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 90,000
ft2
Annual Production 99,000
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,007 1,600,200
kWh
Electricity Demand $39,283 4,469
kW-mo/yr
Electricity Fees $7,019 -
Natural Gas $153,999 11,105
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $133,308 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,285

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.1133: Adjust burners for efficient operation $1,720 $1,800 - - $1,720
-
MMBtu
- - -
02 2.2153: Close off unneeded steam lines $13,322 - - - $13,322
-
MMBtu
- - -
03 2.2113: Repair or replace steam traps $4,704 $1,500 - - $4,704
-
MMBtu
- - -
04 2.2123: Insulate feedwater tank $879 $220 - - $879
-
MMBtu
- - -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,698 $7,600 $1,538
66,000
kWh
$1,160
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $1,146 $1,700 $538
23,080
kWh
$608
-
kW-mo/yr
- - - -
07 2.2437: Recover waste heat from equipment $6,998 - - - $6,998
-
MMBtu
- - -
08 2.4235: Remove or close off unneeded compressed air lines $272 $500 $272
11,670
kWh
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $129 $377 $40
1,714
kWh
$89
-
kW-mo/yr
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,390 $50 $652
28,000
kWh
$738
-
kW-mo/yr
- - - -
11 4.321: Optimize production lot sizes and inventories $20,000 $20,000 - - - $10,000 - $10,000
12 4.321: Optimize production lot sizes and inventories $18,650 $20,000 - - - $2,500 $16,150 -
13 4.131: Modify process to reduce material use/cost $61,400 $25,000 - - - $20,000 $41,400 -
TOTAL RECOMMENDED $133,308 $78,747 $3,040
130,464
kWh
$2,595
-
kW-mo/yr
$27,623
-
MMBtu
$32,500 $57,550 $10,000
TOTAL IMPLEMENTED $49,285 $24,070 $924
39,670
kWh
$738
-
kW-mo/yr
$27,623
-
MMBtu
$10,000 - $10,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs