ITAC Assessment: NC0336
ITAC logo
ITAC Assessment: NC0336
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product plumbing fixtures
NAICS 332913: Plumbing Fixture Fitting and Trim Manufacturing
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $50
M
to 100
M
# of Employees 230
Plant Area 155,000
ft2
Annual Production 350,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $423,742 9,778,000
kWh
Electricity Demand $108,137 25,444
kW-mo/yr
Electricity Fees $202 -
Natural Gas $147,027 14,678
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $166,851 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,616

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.2437: Recover waste heat from equipment $13,979 $24,586 $(-249.0)
(-5,968)
kWh
$(-51.0)
-
kW-mo/yr
$14,279
-
MMBtu
- - -
02 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water $8,595 $1,300 - - - $5,685
-
Tgal
$2,910 -
03 2.1133: Adjust burners for efficient operation $2,620 $1,500 - - $2,620
-
MMBtu
- - -
04 2.8114: Change rate schedules or other changes in utility service $9,620 $20,000 - - $9,620
-
MMBtu
- - -
05 2.2121: Increase amount of condensate returned $12,198 $7,290 - - $8,076
-
MMBtu
- $2,273 $1,849
-
Tgal
06 2.2136: Install / repair insulation on steam lines $2,156 $455 - - $2,156
-
MMBtu
- - -
07 2.7229: Air condition only space necessary $11,658 $6,500 $10,808
241,208
kWh
$850
-
kW-mo/yr
- - - -
08 2.7241: Install outside air damper / economizer on hvac unit $18,883 $20,000 $18,883
451,866
kWh
- - - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,535 $100 $2,938
70,304
kWh
$597
-
kW-mo/yr
- - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $1,046 $1,735 $870
20,818
kWh
$176
-
kW-mo/yr
- - - -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $3,361 $50 $2,337
55,920
kWh
$475
-
kW-mo/yr
- - $549 -
12 4.311: Schedule deliveries according to demand $79,200 $25,000 - - - - $79,200 -
TOTAL RECOMMENDED $166,851 $108,516 $35,587
834,148
kWh
$2,047
-
kW-mo/yr
$36,751
-
MMBtu
$5,685
-
Tgal
$84,932 $1,849
-
Tgal
TOTAL IMPLEMENTED $34,616 $27,390 $21,821
522,170
kWh
$597
-
kW-mo/yr
$8,076
-
MMBtu
- $2,273 $1,849
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs