Assessment Year | 2005 |
---|---|
Principal Product | Automotive belts |
NAICS | 326220: Rubber and Plastics Hoses and Belting Manufacturing |
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $100 M to 500M |
# of Employees | 256 |
Plant Area |
200,000
ft2
|
Annual Production | 12,500,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $776,744 | 17,305,728 |
kWh
|
$0.045 |
Electricity Demand | $114,609 | 28,482 |
kW-mo/yr
|
$4.02 |
Electricity Fees | $38,549 | - |
|
- |
Natural Gas | $938,564 | 139,620 |
MMBtu
|
$6.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $44,886 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,535 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2612: Use cooling tower water instead of refrigeration | $9,148 | $15,000 |
$12,462
389,433
kWh
|
$1,670
-
kW-mo/yr
|
- |
$(-2,509.0)
-
Tgal
|
- | $(-2,475.0) | |
02 | 2.2628: Utilize a less expensive cooling method | $17,625 | $50,000 |
$27,750
867,240
kWh
|
- | - |
$(-6,375.0)
-
Tgal
|
- | $(-3,750.0) | |
03 | 2.1133: Adjust burners for efficient operation | $10,261 | $2,000 | - | - |
$10,261
-
MMBtu
|
- | - | - | |
04 | 2.2163: Use minimum steam operating pressure | $7,578 | $200 | - | - |
$7,578
-
MMBtu
|
- | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $274 | $100 |
$948
29,638
kWh
|
$126
-
kW-mo/yr
|
- | - | $(-400.0) | $(-400.0) | |
TOTAL RECOMMENDED | $44,886 | $67,300 |
$41,160
1,286,311
kWh
|
$1,796
-
kW-mo/yr
|
$17,839
-
MMBtu
|
$(-8,884.0)
-
Tgal
|
$(-400.0) | $(-6,625.0) | ||
TOTAL IMPLEMENTED | $10,535 | $2,100 |
$948
29,638
kWh
|
$126
-
kW-mo/yr
|
$10,261
-
MMBtu
|
- | $(-400.0) | $(-400.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs