ITAC Assessment: NC0313
ITAC logo
ITAC Assessment: NC0313
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Automotive belts
NAICS 326220: Rubber and Plastics Hoses and Belting Manufacturing
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $100
M
to 500
M
# of Employees 256
Plant Area 200,000
ft2
Annual Production 12,500,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $776,744 17,305,728
kWh
Electricity Demand $114,609 28,482
kW-mo/yr
Electricity Fees $38,549 -
Natural Gas $938,564 139,620
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,886 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,535

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings
01 2.2612: Use cooling tower water instead of refrigeration $9,148 $15,000 $12,462
389,433
kWh
$1,670
-
kW-mo/yr
- $(-2,509.0)
-
Tgal
- $(-2,475.0)
02 2.2628: Utilize a less expensive cooling method $17,625 $50,000 $27,750
867,240
kWh
- - $(-6,375.0)
-
Tgal
- $(-3,750.0)
03 2.1133: Adjust burners for efficient operation $10,261 $2,000 - - $10,261
-
MMBtu
- - -
04 2.2163: Use minimum steam operating pressure $7,578 $200 - - $7,578
-
MMBtu
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $274 $100 $948
29,638
kWh
$126
-
kW-mo/yr
- - $(-400.0) $(-400.0)
TOTAL RECOMMENDED $44,886 $67,300 $41,160
1,286,311
kWh
$1,796
-
kW-mo/yr
$17,839
-
MMBtu
$(-8,884.0)
-
Tgal
$(-400.0) $(-6,625.0)
TOTAL IMPLEMENTED $10,535 $2,100 $948
29,638
kWh
$126
-
kW-mo/yr
$10,261
-
MMBtu
- $(-400.0) $(-400.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs