Assessment Year | 2005 |
---|---|
Principal Product | Cases of fruit juice |
NAICS | 311421: Fruit and Vegetable Canning |
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 30 |
Plant Area |
45,000
ft2
|
Annual Production | 1,800,000
pieces
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,111 | 1,439,808 |
kWh
|
$0.048 |
Electricity Demand | $14,554 | 3,881 |
kW-mo/yr
|
$3.75 |
Electricity Fees | $2,972 | - |
|
- |
Fuel Oil #2 | $88,862 | 13,517 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,524 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,371 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2444: Use hot process fluids to preheat incoming process fluids | $6,776 | $6,516 |
$(-180.0)
(-3,740)
kWh
|
$(-84.0)
-
kW-mo/yr
|
$9,540
-
MMBtu
|
- | $(-2,500.0) | - | |
02 | 2.1133: Adjust burners for efficient operation | $1,366 | $1,300 | - | - |
$1,366
-
MMBtu
|
- | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $2,325 | $2,286 | - | - |
$2,325
-
MMBtu
|
- | - | - | |
04 | 2.8115: Base utility charges on usage rather than area occupied | $1,377 | $100 | - | - |
$1,777
-
MMBtu
|
- | - | $(-400.0) | |
05 | 2.1241: Reduce excessive boiler blowdown | $152 | - | - | - |
$136
-
MMBtu
|
$16
-
Tgal
|
- | - | |
06 | 2.4151: Develop a repair/replace policy | $125 | $273 |
$81
1,686
kWh
|
$44
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $169 | $321 |
$134
2,799
kWh
|
$35
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $100 | $100 |
$374
7,800
kWh
|
$176
-
kW-mo/yr
|
- | - | $(-300.0) | $(-150.0) | |
09 | 2.4239: Eliminate or reduce compressed air usage | $134 | $100 |
$91
1,900
kWh
|
$43
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $12,524 | $10,996 |
$500
10,445
kWh
|
$214
-
kW-mo/yr
|
$15,144
-
MMBtu
|
$16
-
Tgal
|
$(-2,800.0) | $(-550.0) | ||
TOTAL IMPLEMENTED | $4,371 | $4,380 |
$680
14,185
kWh
|
$298
-
kW-mo/yr
|
$3,827
-
MMBtu
|
$16
-
Tgal
|
$(-300.0) | $(-150.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Water Disposal Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs