Assessment Year | 2004 |
---|---|
Principal Product | Wooden laboratory cabinets |
NAICS | 337127: Institutional Furniture Manufacturing |
SIC | 3821: Laboratory Apparatus and Furniture |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
153,000
ft2
|
Annual Production | 56,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $161,309 | 4,135,920 |
kWh
|
$0.039 |
Electricity Demand | $61,145 | 9,231 |
kW-mo/yr
|
$6.62 |
Electricity Fees | $6,872 | - |
|
- |
Natural Gas | $80,206 | 9,976 |
MMBtu
|
$8.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $276,801 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $74,571 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.323: Optimize lot sizes to reduce inventory carrying costs | $151,225 | $150,000 |
$1,225
31,400
kWh
|
- | - | $112,500 | $37,500 | |
02 | 4.122: Develop standard procedures to improve internal yields | $72,400 | $49,500 | - | - | - | $16,400 | $56,000 | |
03 | 2.7313: Recycle air for heating, ventilation and air conditioning | $32,361 | $24,000 | - | - |
$32,361
-
MMBtu
|
- | - | |
04 | 2.2437: Recover waste heat from equipment | $16,989 | $31,278 | - | - |
$16,989
-
MMBtu
|
- | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,342 | $1,456 |
$889
22,800
kWh
|
$453
-
kW-mo/yr
|
- | - | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $313 | $381 |
$207
5,301
kWh
|
$106
-
kW-mo/yr
|
- | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,171 | $100 |
$2,432
62,360
kWh
|
$1,239
-
kW-mo/yr
|
- | $(-1,200.0) | $(-300.0) | |
TOTAL RECOMMENDED | $276,801 | $256,715 |
$4,753
121,861
kWh
|
$1,798
-
kW-mo/yr
|
$49,350
-
MMBtu
|
$127,700 | $93,200 | ||
TOTAL IMPLEMENTED | $74,571 | $49,600 |
$2,432
62,360
kWh
|
$1,239
-
kW-mo/yr
|
- | $15,200 | $55,700 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs