| Assessment Year | 2004 |
|---|---|
| Principal Product | Cases of bacon, hams, sausage |
| NAICS | 311611: Animal (except Poultry) Slaughtering |
| SIC | 2011: Meat Packing Plants |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
295,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $781,632 | 21,506,885 |
kWh
|
$0.036 |
| Electricity Demand | $497,821 | 42,545 |
kW-mo/yr
|
$11.70 |
| Electricity Fees | $6,000 | - |
|
- |
| Natural Gas | $261,739 | 54,942 |
MMBtu
|
$4.76 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $72,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $66,940 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7273: Install desiccant humidity control system | $59,627 | $136,000 |
$(-3,972.0)
(-107,800)
kWh
|
$(-1,243.0)
-
kW-mo/yr
|
$(-10,158.0)
-
MMBtu
|
$75,000 | - | |
| 02 | 2.2626: Avoid frost formation on evaporators | $5,926 | $19,000 |
$4,438
120,446
kWh
|
$1,488
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $953 | $100 |
$1,364
37,026
kWh
|
$489
-
kW-mo/yr
|
- | $(-600.0) | $(-300.0) | |
| 04 | 2.1133: Adjust burners for efficient operation | $372 | - | - | - |
$372
-
MMBtu
|
- | - | |
| 05 | 2.1133: Adjust burners for efficient operation | $5,988 | - | - | - |
$5,988
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $72,866 | $155,100 |
$1,830
49,672
kWh
|
$734
-
kW-mo/yr
|
$(-3,798.0)
-
MMBtu
|
$74,400 | $(-300.0) | ||
| TOTAL IMPLEMENTED | $66,940 | $136,100 |
$(-2,608.0)
(-70,774)
kWh
|
$(-754.0)
-
kW-mo/yr
|
$(-3,798.0)
-
MMBtu
|
$74,400 | $(-300.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs