| Assessment Year | 2004 |
|---|---|
| Principal Product | pre-cast concrete structures |
| NAICS | 238120: Structural Steel and Precast Concrete Contractors |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
140,000
ft2
|
| Annual Production | 264,600,000
lb
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $114,542 | 2,588,109 |
kWh
|
$0.044 |
| Electricity Demand | $16,723 | 4,905 |
kW-mo/yr
|
$3.41 |
| Natural Gas | $43,487 | 3,990 |
MMBtu
|
$10.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $8,626 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $693 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4226: Use / purchase optimum sized compressor | $4,343 | $18,000 | n/a |
$4,343
49,600
kWh
|
- |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $458 | $1,750 |
$375
8,200
kWh
|
$83
-
kW-mo/yr
|
|
| 03 | 2.4239: Eliminate or reduce compressed air usage | $47 | $25 |
$37
801
kWh
|
$10
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,132 | $630 |
$2,558
55,965
kWh
|
$574
-
kW-mo/yr
|
|
| 05 | 2.6218: Turn off equipment when not in use | $574 | $25 |
$574
15,120
kWh
|
- | |
| 06 | 2.7134: Use photocell controls | $72 | $130 |
$60
1,314
kWh
|
$12
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $8,626 | $20,560 |
$7,947
131,000
kWh
|
$679
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $693 | $180 |
$671
17,235
kWh
|
$22
-
kW-mo/yr
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs