| Assessment Year | 2003 |
|---|---|
| Principal Product | Paperboard beverage cartons |
| NAICS | 322212: Folding Paperboard Box Manufacturing |
| SIC | 2652: Setup Paperboard Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 163 |
| Plant Area |
300,000
ft2
|
| Annual Production | 66,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $221,067 | 7,983,477 |
kWh
|
$0.028 |
| Electricity Demand | $179,447 | 16,457 |
kW-mo/yr
|
$10.90 |
| Electricity Fees | $13,746 | - |
|
- |
| Natural Gas | $227,253 | 35,195 |
MMBtu
|
$6.46 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,662 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7313: Recycle air for heating, ventilation and air conditioning | $2,058 | $5,954 | - | - |
$2,058
-
MMBtu
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $25,721 | $63,800 |
$19,503
704,068
kWh
|
$27,622
-
kW-mo/yr
|
$(-19,404.0)
-
MMBtu
|
$(-2,000.0) | |
| 03 | 2.2491: Use cooling air which cools hot work pieces for space heating | $12,088 | $7,190 | - | - |
$12,088
-
MMBtu
|
- | |
| 04 | 2.6218: Turn off equipment when not in use | $4,207 | $4,563 |
$4,207
151,870
kWh
|
- | - | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $455 | $683 |
$211
7,620
kWh
|
$244
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,010 | $4,120 |
$1,395
50,359
kWh
|
$1,615
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $47,539 | $86,310 |
$25,316
913,917
kWh
|
$29,481
-
kW-mo/yr
|
$(-5,258.0)
-
MMBtu
|
$(-2,000.0) | ||
| TOTAL IMPLEMENTED | $4,662 | $5,246 |
$4,418
159,490
kWh
|
$244
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs