ITAC Assessment: NC0273
ITAC logo
ITAC Assessment: NC0273
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Finished wood cabinet components
NAICS 337122: Nonupholstered Wood Household Furniture Manufacturing
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 65
Plant Area 173,000
ft2
Annual Production 3,100,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,975 1,286,323
kWh
Electricity Demand $19,106 5,538
kW-mo/yr
Electricity Fees $196 -
LPG $75,213 7,697
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $2,069 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,176

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.2437: Recover waste heat from equipment $705 $500 - - $705
-
MMBtu
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $232 $83 $152
3,160
kWh
$80
-
kW-mo/yr
-
03 2.3132: Recharge batteries on during off-peak demand periods $65 - - $65
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $51 $104 $51
1,065
kWh
- -
05 2.7134: Use photocell controls $137 $200 $110
2,300
kWh
$27
-
kW-mo/yr
-
06 2.7111: Reduce illumination to minimum necessary levels $879 $390 $574
11,960
kWh
$305
-
kW-mo/yr
-
TOTAL RECOMMENDED $2,069 $1,277 $887
18,485
kWh
$477
-
kW-mo/yr
$705
-
MMBtu
TOTAL IMPLEMENTED $1,176 $473 $726
15,120
kWh
$450
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs