ITAC Assessment: NC0261
ITAC logo
ITAC Assessment: NC0261
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Plastic bags and sheeting
NAICS 326111: Plastics Bag and Pouch Manufacturing
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $50
M
to 100
M
# of Employees 394
Plant Area 390,000
ft2
Annual Production 147,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,113,014 43,130,720
kWh
Electricity Demand $892,927 67,346
kW-mo/yr
Electricity Fees $148,006 -
Natural Gas $38,621 4,863
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $457,301 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,840

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Increase in Production Savings
01 2.4151: Develop a repair/replace policy $10,483 $9,992 $5,894
245,597
kWh
$4,589
-
kW-mo/yr
- - - -
02 2.2437: Recover waste heat from equipment $17,622 $2,911 - - $17,622
-
MMBtu
- - -
03 2.2511: Insulate bare equipment $13,615 $5,261 $7,655
318,966
kWh
$5,960
-
kW-mo/yr
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $4,891 $50 $2,750
114,580
kWh
$2,141
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,466 $6,430 $1,390
57,902
kWh
$1,076
-
kW-mo/yr
- - - -
06 2.7111: Reduce illumination to minimum necessary levels $1,314 $500 $739
30,778
kWh
$575
-
kW-mo/yr
- - - -
07 2.2691: Shut off cooling if cold outside air will cool process $910 $3,948 $512
21,334
kWh
$398
-
kW-mo/yr
- - - -
08 4.421: Modify current incentive program $406,000 $41,000 - - - $(-388,000.0) $(-1,146,000.0) $1,940,000
TOTAL RECOMMENDED $457,301 $70,092 $18,940
789,157
kWh
$14,739
-
kW-mo/yr
$17,622
-
MMBtu
$(-388,000.0) $(-1,146,000.0) $1,940,000
TOTAL IMPLEMENTED $17,840 $16,472 $10,034
418,079
kWh
$7,806
-
kW-mo/yr
- - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Primary Raw Material Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs