Assessment Year | 2003 |
---|---|
Principal Product | High density fiberboard |
NAICS | 333243: Sawmill, Woodworking, and Paper Machinery Manufacturing |
SIC | 2490: |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
500,000
ft2
|
Annual Production | 400,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,864,343 | 69,061,800 |
kWh
|
$0.027 |
Electricity Demand | $804,723 | 98,660 |
kW-mo/yr
|
$8.16 |
Electricity Fees | $67,093 | - |
|
- |
Natural Gas | $624,396 | 108,000 |
MMBtu
|
$5.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $576,774 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,389 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $219,783 | $413,700 |
$175,961
6,517,056
kWh
|
$43,822
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $58,067 | $15,000 |
$42,039
1,556,994
kWh
|
$16,028
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.1331: Burn a less expensive grade of fuel | $182,984 | $375,000 | - | - |
$291,312
-
MMBtu
|
$(-93,328.0)
-
MMBtu
|
$(-15,000.0) | - | |
04 | 4.211: Consider use / purchase of bulk materials where possible | $110,788 | $400,000 |
$(-26,575.0)
(-984,251)
kWh
|
$(-10,137.0)
-
kW-mo/yr
|
- | - | $(-10,000.0) | $157,500 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,508 | $50 |
$1,814
67,200
kWh
|
$694
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2511: Insulate bare equipment | $763 | $1,147 | - | - | - |
$763
-
MMBtu
|
- | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,881 | $600 |
$1,361
50,400
kWh
|
$520
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $576,774 | $1,205,497 |
$194,600
7,207,399
kWh
|
$50,927
-
kW-mo/yr
|
$291,312
-
MMBtu
|
$(-92,565.0)
-
MMBtu
|
$(-25,000.0) | $157,500 | ||
TOTAL IMPLEMENTED | $4,389 | $650 |
$3,175
117,600
kWh
|
$1,214
-
kW-mo/yr
|
- | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Wood Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs