Assessment Year | 2002 |
---|---|
Principal Product | Aluminum extrusions |
NAICS |
n/a
|
SIC | 3354: Aluminum Extruded Products |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
130,000
ft2
|
Annual Production | 15,000,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $401,600 | 8,172,000 |
kWh
|
$0.049 |
Electricity Demand | $101,502 | 20,757 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $2,215 | - |
|
- |
Natural Gas | $325,509 | 53,072 |
MMBtu
|
$6.13 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,741 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,272 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3522: Increase electrical conductor size to reduce distribution losses | $29,079 | $130,000 |
$25,488
514,080
kWh
|
$3,591
-
kW-mo/yr
|
- | |
02 | 2.2437: Recover waste heat from equipment | $50,797 | $100,000 | - | - |
$50,797
-
MMBtu
|
|
03 | 2.2444: Use hot process fluids to preheat incoming process fluids | $4,593 | $7,000 | - | - |
$4,593
-
MMBtu
|
|
04 | 2.5122: Replace high resistance ducts, pipes, and fittings | $6,367 | $10,000 |
$5,581
112,560
kWh
|
$786
-
kW-mo/yr
|
- | |
05 | 2.1133: Adjust burners for efficient operation | $4,768 | $10,000 | - | - |
$4,768
-
MMBtu
|
|
06 | 2.2511: Insulate bare equipment | $137 | $574 |
$113
2,262
kWh
|
$24
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $95,741 | $257,574 |
$31,182
628,902
kWh
|
$4,401
-
kW-mo/yr
|
$60,158
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,272 | $20,574 |
$5,694
114,822
kWh
|
$810
-
kW-mo/yr
|
$4,768
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs