| Assessment Year | 2002 |
|---|---|
| Principal Product | Upholstery fabric |
| NAICS |
n/a
|
| SIC | 2210: |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
200,000
ft2
|
| Annual Production | 13,000
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $323,177 | 12,149,500 |
kWh
|
$0.027 |
| Electricity Demand | $222,638 | 23,635 |
kW-mo/yr
|
$9.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,244 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6125: Keep equipment clean | $20,000 | $10,600 | n/a | - | - | $20,000 | - |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $1,557 | - | n/a |
$83
3,130
kWh
|
$1,474
-
kW-mo/yr
|
- | - |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $12,181 | $500 | n/a |
$8,089
304,080
kWh
|
$4,092
-
kW-mo/yr
|
- | - |
| 04 | 2.4239: Eliminate or reduce compressed air usage | $621 | $290 | n/a |
$91
3,407
kWh
|
$530
-
kW-mo/yr
|
- | - |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $68 | - | n/a |
$68
2,555
kWh
|
- | - | - |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $2,159 | $2,600 | n/a |
$1,454
54,662
kWh
|
$705
-
kW-mo/yr
|
- | - |
| 07 | 2.3132: Recharge batteries on during off-peak demand periods | $658 | - | n/a | - |
$658
-
kW-mo/yr
|
- | - |
| 08 | 4.431: Train operators for maximum operating efficiency | $10,000 | $10,000 | n/a | - | - | - | $10,000 |
| TOTAL RECOMMENDED | $47,244 | $23,990 |
$9,785
367,834
kWh
|
$7,459
-
kW-mo/yr
|
$20,000 | $10,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs