Assessment Year | 2002 |
---|---|
Principal Product | Laminated board |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
100,000
ft2
|
Annual Production | 12,500
thousand feet
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,466 | 1,766,700 |
kWh
|
$0.048 |
Electricity Demand | $30,476 | 6,969 |
kW-mo/yr
|
$4.37 |
LPG | $29,472 | 3,357 |
MMBtu
|
$8.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $167,807 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat | $142,297 | $262,500 |
$44,530
931,400
kWh
|
$11,179
-
kW-mo/yr
|
$21,783
-
MMBtu
|
$64,805
-
lb
|
- | - | |
02 | 2.4323: Use optimum size and capacity equipment | $7,452 | $20,000 |
$6,110
127,788
kWh
|
$1,342
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,574 | - | - |
$15,574
-
kW-mo/yr
|
- | - | $(-10,000.0) | - | |
04 | 2.2437: Recover waste heat from equipment | $3,991 | $1,000 | - | - |
$3,991
-
MMBtu
|
- | - | - | |
05 | 4.515: Install shelves / racks to utilize unused space | $7,000 | $6,320 | - | - | - | - | $3,000 | $4,000 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $893 | $1,590 |
$709
14,838
kWh
|
$184
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $600 | - |
$396
8,280
kWh
|
$204
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $167,807 | $291,410 |
$51,745
1,082,306
kWh
|
$28,483
-
kW-mo/yr
|
$25,774
-
MMBtu
|
$64,805
-
lb
|
$(-7,000.0) | $4,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs