ITAC Assessment: NC0245
ITAC logo
ITAC Assessment: NC0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Laminated board
NAICS
n/a
SIC 2493: Reconstituted Wood Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 100,000
ft2
Annual Production 12,500
thousand feet
Production Hrs. Annual 4,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,466 1,766,700
kWh
Electricity Demand $30,476 6,969
kW-mo/yr
LPG $29,472 3,357
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $167,807 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
01 2.3411: Replace electric motors with back pressure steam turbines and use exhaust steam for process heat $142,297 $262,500 $44,530
931,400
kWh
$11,179
-
kW-mo/yr
$21,783
-
MMBtu
$64,805
-
lb
- -
02 2.4323: Use optimum size and capacity equipment $7,452 $20,000 $6,110
127,788
kWh
$1,342
-
kW-mo/yr
- - - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,574 - - $15,574
-
kW-mo/yr
- - $(-10,000.0) -
04 2.2437: Recover waste heat from equipment $3,991 $1,000 - - $3,991
-
MMBtu
- - -
05 4.515: Install shelves / racks to utilize unused space $7,000 $6,320 - - - - $3,000 $4,000
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $893 $1,590 $709
14,838
kWh
$184
-
kW-mo/yr
- - - -
07 2.7124: Make a practice of turning off lights when not needed $600 - $396
8,280
kWh
$204
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $167,807 $291,410 $51,745
1,082,306
kWh
$28,483
-
kW-mo/yr
$25,774
-
MMBtu
$64,805
-
lb
$(-7,000.0) $4,000
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs