ITAC Assessment: NC0231
ITAC logo
ITAC Assessment: NC0231
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Forms, labels, envelopes, and prints
NAICS
n/a
SIC 2761: Manifold Business Forms
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 200,000
ft2
Annual Production 132,000
thousand feet
Production Hrs. Annual 8,400
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $172,267 6,280,560
kWh
Electricity Demand $127,525 13,306
kW-mo/yr
Electricity Fees $9,435 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,850 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $29,626

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4151: Develop a repair/replace policy $2,088 $2,383 $1,401
51,147
kWh
$687
-
kW-mo/yr
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $324 $736 $220
8,019
kWh
$104
-
kW-mo/yr
- -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,818 $830 $808
29,490
kWh
$4,010
-
kW-mo/yr
- -
04 2.7124: Make a practice of turning off lights when not needed $4,994 $200 $4,994
182,242
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $29,626 - $274
10,012
kWh
$566
-
kW-mo/yr
$(-14.0) $28,800
TOTAL RECOMMENDED $41,850 $4,149 $7,697
280,910
kWh
$5,367
-
kW-mo/yr
$(-14.0) $28,800
TOTAL IMPLEMENTED $29,626 - $274
10,012
kWh
$566
-
kW-mo/yr
$(-14.0) $28,800
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs