ITAC Assessment: NC0179
ITAC logo
ITAC Assessment: NC0179
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Painted parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 11
Plant Area 48,000
ft2
Annual Production 50,000
pieces
Production Hrs. Annual 2,000
hrs
Location (State) South Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $21,245 443,728
kWh
Electricity Demand $8,565 2,202
kW-mo/yr
Electricity Fees $29 -
Natural Gas $22,821 4,207
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,681 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,268

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
01 2.7124: Make a practice of turning off lights when not needed $453 $340 $304
6,448
kWh
$149
-
kW-mo/yr
- - - -
02 2.7134: Use photocell controls $128 $120 $105
2,052
kWh
$23
-
kW-mo/yr
- - - -
03 2.7131: Add area lighting switches $121 $640 $82
1,758
kWh
$39
-
kW-mo/yr
- - - -
04 2.2437: Recover waste heat from equipment $164 $800 - - $164
-
MMBtu
- - -
05 3.4153: Use counter current rinsing to reduce waste water $4,315 $1,425 $(-36.0)
(-879)
kWh
$(-17.0)
-
kW-mo/yr
- - $4,368
-
Tgal
-
06 4.652: Replace existing equipment with more suitable substitutes $4,000 $2,500 - - - $4,000 - -
07 4.611: Begin a practice of predictive / preventative maintenance $500 - - - - - - $500
TOTAL RECOMMENDED $9,681 $5,825 $455
9,379
kWh
$194
-
kW-mo/yr
$164
-
MMBtu
$4,000 $4,368
-
Tgal
$500
TOTAL IMPLEMENTED $5,268 $1,765 $268
5,569
kWh
$132
-
kW-mo/yr
- - $4,368
-
Tgal
$500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Water Consumption Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs