ITAC Assessment: NC0175
ITAC logo
ITAC Assessment: NC0175
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Packaged medical supplies
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 100,000
ft2
Annual Production 2,200,000,000
pieces
Production Hrs. Annual 6,000
hrs
Location (State) North Carolina

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $125,347 4,802,755
kWh
Electricity Demand $85,768 8,970
kW-mo/yr
Electricity Fees $597 -
Natural Gas $19,966 3,451
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $94,161 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings
01 4.424: Improve space comfort conditioning $2,400 $1,000 n/a - - - - $2,400 - - -
02 4.131: Modify process to reduce material use/cost $52,800 $1,000 n/a - - - - - $52,800 - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $3,698 $3,000 n/a $3,698
142,145
kWh
- - - - - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $8,887 $8,000 n/a $4,774
183,763
kWh
$8,647
-
kW-mo/yr
$(-4,534.0)
-
MMBtu
- - - - -
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,727 $5,500 n/a $4,160
160,023
kWh
$4,522
-
kW-mo/yr
$(-3,955.0)
-
MMBtu
- - - - -
06 3.4111: Use closed cycle process to minimize waste water production $2,424 $500 n/a $725
27,843
kWh
$1,311
-
kW-mo/yr
- - - - $100 $288
-
Tgal
07 3.5315: Lease / purchase baler; sell cardboard to recycler $1,920 $500 n/a - - - $1,920
-
lb
- - - -
08 3.4154: Eliminate leaks in water lines and valves $1,172 $200 n/a $826
41,911
kWh
- - - - - - $346
-
Tgal
09 3.4114: Replace city water with recycled water via cooling tower $16,133 $1,000 n/a - - - - - - - $16,133
-
Tgal
TOTAL RECOMMENDED $94,161 $20,700 $14,183
555,685
kWh
$14,480
-
kW-mo/yr
$(-8,489.0)
-
MMBtu
$1,920
-
lb
$2,400 $52,800 $100 $16,767
-
Tgal
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs