| Assessment Year | 1999 |
|---|---|
| Principal Product | Dyed synthetic yarns |
| NAICS |
n/a
|
| SIC | 2281: Yarn Spinning Mills |
| Sales Range | $50 M to 100M |
| # of Employees | 433 |
| Plant Area |
230,000
ft2
|
| Annual Production | 40,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $540,384 | 23,501,759 |
kWh
|
$0.023 |
| Electricity Demand | $564,541 | 59,930 |
kW-mo/yr
|
$9.42 |
| Electricity Fees | $3,587 | - |
|
- |
| Natural Gas | $688,338 | 196,696 |
MMBtu
|
$3.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $102,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Natural Gas Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $11,533 | $10,000 |
$11,533
-
MMBtu
|
- | - | - | - | - | |
| 02 | 2.2425: Use flue gases to heat process or service water | $38,680 | $200,000 |
$40,901
-
MMBtu
|
- | - | - | - |
$(-2,221.0)
-
Tgal
|
|
| 03 | 3.4154: Eliminate leaks in water lines and valves | $34,792 | $5,000 |
$21,601
-
MMBtu
|
$12,191
-
Tgal
|
- | - | $1,000 | - | |
| 04 | 3.6124: Burn waste oil for heat | $787 | $2,000 |
$259
-
MMBtu
|
- |
$528
-
gal
|
- | - | - | |
| 05 | 3.4155: Meter waste water | $16,740 | $3,500 | - | - | - |
$16,740
-
lb
|
- | - | |
| TOTAL RECOMMENDED | $102,532 | $220,500 |
$74,294
-
MMBtu
|
$12,191
-
Tgal
|
$528
-
gal
|
$16,740
-
lb
|
$1,000 |
$(-2,221.0)
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs