Assessment Year | 1999 |
---|---|
Principal Product | Picture frame moulding |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 34 |
Plant Area |
60,000
ft2
|
Annual Production | 3,000
thousand feet
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $25,847 | 559,496 |
kWh
|
$0.046 |
Electricity Demand | $22,251 | 3,829 |
kW-mo/yr
|
$5.81 |
Fuel Oil #2 | $14,557 | 2,366 |
MMBtu
|
$6.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $100,980 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $27,976 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1133: Adjust burners for efficient operation | $1,244 | $2,400 | - | - |
$1,244
-
MMBtu
|
- | - | - | |
02 | 2.7313: Recycle air for heating, ventilation and air conditioning | $6,230 | $19,535 | - | - |
$6,230
-
MMBtu
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $489 | $1,100 |
$489
10,551
kWh
|
- | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $1,229 | $5,323 |
$716
15,533
kWh
|
$513
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $503 | $143 |
$281
6,155
kWh
|
$222
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.6123: Burn wood by-products for heat | $22,545 | $80,500 |
$4,818
104,338
kWh
|
$3,632
-
kW-mo/yr
|
$5,095
-
MMBtu
|
$9,000
-
lb
|
- | - | |
07 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $43,740 | $9,500 | - | - | - | - | $43,740 | - | |
08 | 4.322: Eliminate old stock and modify inventory control | $25,000 | $1,000 | - | - | - | - | - | $25,000 | |
TOTAL RECOMMENDED | $100,980 | $119,501 |
$6,304
136,577
kWh
|
$4,367
-
kW-mo/yr
|
$12,569
-
MMBtu
|
$9,000
-
lb
|
$43,740 | $25,000 | ||
TOTAL IMPLEMENTED | $27,976 | $8,866 |
$997
21,688
kWh
|
$735
-
kW-mo/yr
|
$1,244
-
MMBtu
|
- | - | $25,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs