Assessment Year | 1999 |
---|---|
Principal Product | Ready to assemble bookcases |
NAICS |
n/a
|
SIC | 2511: Wood Household Furniture, Except Upholstered |
Sales Range | $10 M to 50M |
# of Employees | 135 |
Plant Area |
150,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $63,260 | 1,342,907 |
kWh
|
$0.047 |
Electricity Demand | $34,034 | 6,960 |
kW-mo/yr
|
$4.89 |
Electricity Fees | $3,272 | - |
|
- |
Natural Gas | $14,152 | 2,274 |
MMBtu
|
$6.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $169,442 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,140 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $1,160 | $500 | - | - |
$1,160
-
MMBtu
|
- | - | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,328 | $20 |
$1,328
28,136
kWh
|
- | - | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,140 | $1,650 | - |
$8,015
-
kW-mo/yr
|
- | - | $(-1,875.0) | - | |
04 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $160,533 | $279,000 |
$38,957
1,598,476
kWh
|
- |
$18,859
-
MMBtu
|
$82,717
-
lb
|
- | $20,000 | |
05 | 3.6121: Burn waste paper for heat | $281 | - | - | - | - |
$281
-
lb
|
- | - | |
TOTAL RECOMMENDED | $169,442 | $281,170 |
$40,285
1,626,612
kWh
|
$8,015
-
kW-mo/yr
|
$20,019
-
MMBtu
|
$82,998
-
lb
|
$(-1,875.0) | $20,000 | ||
TOTAL IMPLEMENTED | $6,140 | $1,650 | - |
$8,015
-
kW-mo/yr
|
- | - | $(-1,875.0) | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs