Assessment Year | 1999 |
---|---|
Principal Product | Nylon 6,6 filament yarn |
NAICS |
n/a
|
SIC | 2280: |
Sales Range | $10 M to 50M |
# of Employees | 128 |
Plant Area |
160,000
ft2
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $669,509 | 28,528,136 |
kWh
|
$0.023 |
Electricity Demand | $754,011 | 46,888 |
kW-mo/yr
|
$16.08 |
Electricity Fees | $207,042 | - |
|
- |
LPG | $18,281 | 2,243 |
MMBtu
|
$8.15 |
Fuel Oil #2 | $55,960 | 13,167 |
MMBtu
|
$4.25 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $109,374 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,587 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,733 | $1,400 | - | - | - |
$2,733
-
MMBtu
|
- | - | - | |
02 | 2.2437: Recover waste heat from equipment | $2,043 | $2,000 |
$2,043
87,632
kWh
|
- | - | - | - | - | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $30,992 | $6,000 |
$26,648
1,139,215
kWh
|
$24,991
-
kW-mo/yr
|
- |
$(-20,647.0)
-
MMBtu
|
- | - | - | |
04 | 2.7145: Install skylights | $1,207 | $2,000 |
$323
13,775
kWh
|
$884
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.3192: Use fossil fuel powered generator during peak demand periods | $21,795 | $20,000 |
$1,404
60,082
kWh
|
$28,836
-
kW-mo/yr
|
$(-3,445.0)
-
MMBtu
|
- | - | $(-5,000.0) | - | |
06 | 3.4154: Eliminate leaks in water lines and valves | $1,045 | $1,550 | - | - | - |
$966
-
MMBtu
|
$79
-
Tgal
|
- | - | |
07 | 4.212: Adopt in-house material generation | $49,559 | $100,000 |
$(-4,715.0)
(-201,641)
kWh
|
$(-8,843.0)
-
kW-mo/yr
|
- | - | - | - | $63,117 | |
TOTAL RECOMMENDED | $109,374 | $132,950 |
$25,703
1,099,063
kWh
|
$45,868
-
kW-mo/yr
|
$(-3,445.0)
-
MMBtu
|
$(-16,948.0)
-
MMBtu
|
$79
-
Tgal
|
$(-5,000.0) | $63,117 | ||
TOTAL IMPLEMENTED | $56,587 | $106,950 |
$(-2,349.0)
(-100,234)
kWh
|
$(-7,959.0)
-
kW-mo/yr
|
- |
$3,699
-
MMBtu
|
$79
-
Tgal
|
- | $63,117 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #1 Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs