Assessment Year | 1998 |
---|---|
Principal Product | Electrical connectors |
NAICS |
n/a
|
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 187 |
Plant Area |
132,600
ft2
|
Annual Production | 7,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $240,402 | 7,374,267 |
kWh
|
$0.033 |
Electricity Demand | $178,718 | 15,886 |
kW-mo/yr
|
$11.25 |
Electricity Fees | $7,168 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,538 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,729 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $4,388 | $1,000 |
$4,388
131,301
kWh
|
- | - | - | - | - | - | |
02 | 2.4323: Use optimum size and capacity equipment | $3,988 | $13,000 |
$3,988
119,578
kWh
|
- | - | - | - | - | - | |
03 | 2.2514: Cover open tanks | $1,006 | $100 |
$601
17,878
kWh
|
$405
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.7111: Reduce illumination to minimum necessary levels | $396 | $80 |
$234
7,034
kWh
|
$162
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $3,160 | - |
$3,160
94,666
kWh
|
- | - | - | - | - | - | |
06 | 3.5112: Reprocess spent oils on site for re-use | $3,010 | $5,000 | - | - | - |
$550
-
gal
|
- | $2,460 | - | |
07 | 3.5313: Increase amount of waste recovered for resale | $563 | $200 | - | - | - | - |
$563
-
lb
|
- | - | |
08 | 3.4114: Replace city water with recycled water via cooling tower | $16,777 | $4,000 |
$(-107.0)
(-3,224)
kWh
|
$(-216.0)
-
kW-mo/yr
|
$17,100
-
Tgal
|
- | - | - | - | |
09 | 4.511: Expand operations into unused space | $31,250 | $12,850 | - | - | - | - | - | - | $31,250 | |
TOTAL RECOMMENDED | $64,538 | $36,230 |
$12,264
367,233
kWh
|
$351
-
kW-mo/yr
|
$17,100
-
Tgal
|
$550
-
gal
|
$563
-
lb
|
$2,460 | $31,250 | ||
TOTAL IMPLEMENTED | $4,729 | $300 |
$3,761
112,544
kWh
|
$405
-
kW-mo/yr
|
- | - |
$563
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs