Assessment Year | 1998 |
---|---|
Principal Product | Decorative door glass |
NAICS |
n/a
|
SIC | 3210: |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
68,000
ft2
|
Annual Production | 750,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $156,302 | 4,272,567 |
kWh
|
$0.037 |
Electricity Demand | $59,673 | 23,546 |
kW-mo/yr
|
$2.53 |
Electricity Fees | $15,052 | - |
|
- |
Natural Gas | $11,899 | 1,599 |
MMBtu
|
$7.44 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $93,762 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,568 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $79,194 | $118,650 |
$69,920
1,398,886
kWh
|
$9,274
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,438 | $100 | - | - | $1,438 | - | - | - | - | |
03 | 4.214: Purchase appropriately sized material | $6,400 | $1,000 | - | - | - | - |
$3,400
-
gal
|
- | $3,000 | |
04 | 3.5313: Increase amount of waste recovered for resale | $938 | $200 | - | - | - | - | - |
$938
-
lb
|
- | |
05 | 3.8143: Recycle cleaning solvent and reuse | $1,472 | $100 | - | - | - | - |
$912
-
gal
|
- | $560 | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $4,320 | $800 | - | - | - |
$4,320
-
Tgal
|
- | - | - | |
TOTAL RECOMMENDED | $93,762 | $120,850 |
$69,920
1,398,886
kWh
|
$9,274
-
kW-mo/yr
|
$1,438 |
$4,320
-
Tgal
|
$4,312
-
gal
|
$938
-
lb
|
$3,560 | ||
TOTAL IMPLEMENTED | $14,568 | $2,200 | - | - | $1,438 |
$4,320
-
Tgal
|
$4,312
-
gal
|
$938
-
lb
|
$3,560 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs