Assessment Year | 1998 |
---|---|
Principal Product | Insulin |
NAICS |
n/a
|
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $10 M to 50M |
# of Employees | 147 |
Plant Area |
99,500
ft2
|
Annual Production | 12,000,000
pieces
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $371,526 | 11,399,766 |
kWh
|
$0.033 |
Electricity Demand | $214,200 | 19,040 |
kW-mo/yr
|
$11.25 |
Electricity Fees | $32,671 | - |
|
- |
Natural Gas | $275,337 | 59,063 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $629,961 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $606,528 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $4,797 | $7,696 |
$2,357
72,392
kWh
|
$2,440
-
kW-mo/yr
|
- | - | - | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $3,905 | $1,400 | - | - |
$3,905
-
MMBtu
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,181 | $27,560 |
$456
14,068
kWh
|
$4,725
-
kW-mo/yr
|
- | - | - | |
04 | 3.4115: Recover and reuse cooling water | $97,026 | $2,000 | - | - | - |
$97,026
-
Tgal
|
- | |
05 | 3.4151: Minimize water usage | $18,252 | $35,000 | - | - | - |
$18,252
-
Tgal
|
- | |
06 | 4.451: Add additional production shift | $500,800 | - | - | - | - | - | $500,800 | |
TOTAL RECOMMENDED | $629,961 | $73,656 |
$2,813
86,460
kWh
|
$7,165
-
kW-mo/yr
|
$3,905
-
MMBtu
|
$115,278
-
Tgal
|
$500,800 | ||
TOTAL IMPLEMENTED | $606,528 | $11,096 |
$2,357
72,392
kWh
|
$2,440
-
kW-mo/yr
|
$3,905
-
MMBtu
|
$97,026
-
Tgal
|
$500,800 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs