Assessment Year | 1997 |
---|---|
Principal Product | Engine components |
NAICS |
n/a
|
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $50 M to 100M |
# of Employees | 185 |
Plant Area |
120,000
ft2
|
Annual Production | 40,000,000
lb
|
Production Hrs. Annual | 8,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $240,268 | 7,052,755 |
kWh
|
$0.034 |
Electricity Demand | $226,362 | 12,329 |
kW-mo/yr
|
$18.36 |
Electricity Fees | $20,723 | - |
|
- |
Natural Gas | $14,138 | 2,220 |
MMBtu
|
$6.37 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $206,904 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $129,253 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $34,969 | $195,000 |
$14,759
432,884
kWh
|
$20,210
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.4239: Eliminate or reduce compressed air usage | $7,740 | $1,600 |
$1,826
40,445
kWh
|
$5,914
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $25,586 | - | - |
$25,586
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.7145: Install skylights | $7,876 | $40,250 |
$1,708
50,117
kWh
|
$6,168
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,480 | $4,200 | - | - | - |
$840
-
lb
|
- | $(-500.0) | - | - | $1,140 | |
06 | 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid | $129,253 | $33,480 | - | - |
$12,724
-
MMBtu
|
- | $9,072 | - | $103,200 | $4,257 | - | |
TOTAL RECOMMENDED | $206,904 | $274,530 |
$18,293
523,446
kWh
|
$57,878
-
kW-mo/yr
|
$12,724
-
MMBtu
|
$840
-
lb
|
$9,072 | $(-500.0) | $103,200 | $4,257 | $1,140 | ||
TOTAL IMPLEMENTED | $129,253 | $33,480 | - | - |
$12,724
-
MMBtu
|
- | $9,072 | - | $103,200 | $4,257 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs